EXECUTIVE SUMMARY |
||
Introduction |
4 |
|
Summary of Construction Works
undertaken during the Reporting Quarter |
4 |
|
Environmental Monitoring and Audit
Works |
4-5 |
|
Air Quality |
5 |
|
Construction Noise |
5 |
|
Ecological Monitoring |
5 |
|
Environmental Non-Compliance |
5 |
|
Environmental Complaint |
5 |
|
Notification of Summons and
Successful Prosecutions |
5 |
|
Future Key Issues |
5-6 |
|
|
|
|
1 |
INTRODUCTION |
|
Purpose of the report |
7 |
|
Structure of the report |
7 |
|
|
|
|
2 |
PROJECT INFORMATION |
|
Background |
8 |
|
Project Organization |
8-9 |
|
Summary of Construction Works
Undertaken During Reporting Quarter |
9 |
|
Status of Environmental Licences,
Notifications and Permits |
9-10 |
|
Summary of EM&A Requirement |
10 |
|
|
|
|
3 |
ENVIRONMENTAL MONITORING
AND AUDIT REQUIREMENT |
|
Monitoring Parameters and Monitoring
Locations |
11-12 |
|
Monitoring Methodology and
Calibration Details |
12 |
|
Environmental Quality Performance
Limits (Action and Limit Levels) |
12 |
|
Landscape and visual |
12 |
|
Ecology Monitoring |
12-13 |
|
Site Audit Summary |
13 |
|
Environmental Mitigation Measures |
13 |
|
Status of Waste Management |
13 |
|
|
|
|
4 |
MONITORING RESULTS |
14 |
Weather Conditions |
14 |
|
Air Quality |
14 |
|
Construction Noise |
14-15 |
|
Ecological Monitoring |
15 |
|
|
|
|
|
|
|
5 |
ENVIRONMENTAL SITE
INSPECTION |
|
Site Audits |
16 |
|
Implementation Status of
Environmental Mitigation Measures |
16 |
|
Solid and Liquid Waste Management
Status |
16 |
|
|
|
|
6 |
NON-COMPLIANCE
(EXCEEDANCES) OF THE ENVIRONMENTAL |
|
QUALITY PERFORMANCE
LIMITS (ACTION AND LIMIT LEVELS) |
|
|
Summary of Exceedances |
17 |
|
Summary of Environmental
Non-Compliance |
17 |
|
Summary of Environmental Complaint |
17 |
|
Summary of Environmental Summon and
Successful Prosecution |
17 |
|
|
|
|
7 |
FUTURE KEY ISSUES |
|
Key Issues in the Coming Three
Months |
18-19 |
|
|
|
|
8 |
CONCLUSIONS AND
RECOMMENDATIONS |
|
Conclusions |
20 |
|
Recommendations |
20-22 |
LIST OF TABLES |
|
Table I |
Summary Table for Events Recorded in
the Reporting Quarter |
Table 2.1 |
Key Contacts of the Project |
Table 2.2 |
Status of Environmental Licences,
Notifications and Permits |
Table 3.1 |
Location for Air Quality Monitoring
Stations |
Table 3.2 |
Impact Air Quality Monitoring
Parameters, Frequency and Duration |
Table 3.3 |
Location of Noise Monitoring
Stations |
Table 3.4 |
Noise Monitoring Parameters,
Duration and Frequency |
Table 4.1 |
Summary of 1-hour TSP Monitoring
Result in Reporting Quarter |
Table 4.2 |
Summary of Noise Monitoring Result
in Reporting Quarter |
LIST OF FIGURES |
|
Figure 1 |
|
Figure 2 |
|
Figure 3 |
|
LIST OF APPENDICES |
|
Appendix A |
|
Appendix B |
|
Appendix C |
|
Appendix D |
|
Appendix E |
|
Appendix F |
|
Appendix G |
|
Appendix H |
|
Appendix I |
|
Appendix J |
EXECUTIVE SUMMARY
Introduction
1.
This is the 5th Quarterly Environmental
Monitoring and Audit (EM&A) Report for the Project of Police Facilities in
Kong Nga Po under Environmental Permit No. FEP-01/510/2016. This report was
prepared by Ka Shing Management Consultancy Ltd. (Ka Shing) under “Service
Contract Quotation No. PMB202/8480/2022/A01/A Provision of Environmental Team
consultancy for Design and Construction of Kong Nga Po Police Training
Facilities” (hereinafter called the “Service Contract”). This report documents
the findings of Environmental Monitoring and Audit (EM&A) work conducted
from April to June 2024.
2.
During the reporting quarterly, the following
Works Contracts were undertaken for the Project of Police Facilities in Kong
Nga Po under Environmental Permit No. FEP-01/510/2016:
l
Contract No. SSK509 - Design and Construction
of Kong Nga Po Police Training Facilities
Summary of Construction Works undertaken during the
Reporting Quarter
3.
The major site activities undertaken in the
reporting quarter included:
l Open cut
excavation
l Removal of
soil
l Construction
of footings
l Mock-up
construction
l Construction
of substructure
l Construction
of footbridge
l Backfilling
l U.U. Lead in and Pipe Duct Connection
Environmental Monitoring and Audit Works
4.
Environmental monitoring for the Project was
performed in accordance with the EM&A Manual and the monitoring results
were checked and reviewed. Site Inspections/Audits were conducted once per
week. The implementation of the environmental mitigation measures, Event Action
Plans and environmental complaint handling procedures were also checked.
5.
Summary of the environmental exceedances of
the reporting quarter for the Project is tabulated in Table I.
Table I
Summary Table for Events Recorded in the Reporting Quarter
Environmental
Monitoring |
Parameter |
No. of
Non-Project related Exceedances |
No. of
Exceedance related to the Construction Works of the Contract |
Action
Taken |
||
Action
Level |
Limit
Level |
Action
Level |
Limit
Level |
|||
Air Quality |
1-hr TSP |
0 |
0 |
0 |
0 |
N/A |
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
N/A |
Air Quality
6. All
construction air quality monitoring was conducted as scheduled in the reporting
quarter. No Action/Limit Level exceedance was recorded in the reporting
quarter.
Construction Noise
7. All
Construction noise monitoring was conducted as scheduled in the reporting
quarter. No Action/Limit Level exceedance was recorded in the reporting
quarter.
Ecological Monitoring
8. All
ecological monitoring was conducted as scheduled in the reporting quarter. The
ecological monitoring photo records and results were shown in the relevant
Monthly EM&A Reports.
Environmental Non-Compliance
9. No
environmental non-compliance was recorded in the reporting quarter.
Environmental Complaint
10. One
environmental complaint was received in the reporting quarter. The Complaint
Log is presented in Appendix I.
Notification of Summons and Successful Prosecutions
11. No
notification of summons or successful environmental prosecutions was received
in the reporting quarter.
Future Key Issues
12. The
major site activities for the coming three months include:
l
Open cut excavation
l
Removal of soil
l
Construction of footings
l
Construction of pile cap
l
Construction of substructure
l
Construction of footbridge
l
Backfilling
l
Mock up construction
l
U.U. Lead in and Pipe Duct Connection
13. Potential
environmental impacts arising from the above construction activities are mainly
associated with construction dust, noise, water quality and waste management.
The anticipated major impacts from the construction works and corresponding
recommended mitigation measures are detailed in Appendix G of Site Audit
Summary.
1 INTRODUCTION
1.1
Ka Shing Management Consultancy Ltd. (Ka
Shing) was commissioned by the Architectural Services Department (ASD) as the
Environmental Team to undertake the Environmental Monitoring and Audit
(EM&A) works for the Project of Police Facilities in Kong Nga Po under
Environmental Permit No. FEP-01/510/2016 to ensure that the environmental
performance of the Works Contracts comply with the requirements specified in
the Environmental Permits (EPs), Environmental Impact Assessment (EIA) Report
and Environmental Monitoring & Audit (EM&A) Manual of the Police
Facilities in Kong Nga Po Project and other relevant statutory requirements.
Purpose of the report
1.2
This is the 5th Quarterly EM&A Report
which summarises the impact monitoring results and audit findings for the
EM&A programme during the reporting period from April to June 2024.
Structure of the report
1.3 The
structure of the report is as follows:
Section 1: Introduction - purpose and structure of
the report.
Section 2: Project Information – summarises background
and scope of the Project,
site description,
project organisation and contact details,
construction programme, the construction works undertaken and the status of
Environmental Permits/Licences during the reporting period.
Section 3: Environmental Monitoring and Audit
Requirement – summarises monitoring location and parameters, monitoring
programmes, monitoring frequencies, Action and Limit Levels, Event / Action
Plans, and Site Audit inspection.
Section 4: Monitoring Result – summarises the
monitoring results in the reporting quarter.
Section 5: Environmental Site Inspection – summarises
the audit findings of the weekly site inspections undertaken within the
reporting period.
Section 6: Non-Compliance of the Environmental Quality
Performance Limits (Action and Limit) – summarises any monitoring
exceedance, environmental complaints, environmental summons and successful
prosecutions within the reporting period.
Section 7: Future Key Issues – summarises the
impact forecast and monitoring schedule for the next three months.
Section 8: Conclusions and Recommendations
2
PROJECT INFORMATION
Background
2.1 The
Project mainly includes construction and operation of various police facilities. The
police facilities include:
(i)
a helipad;
(ii) two firing ranges; and
(iii) other facilities, associated
infrastructure & utilities, etc.
2.2 The
Project is a Designated Project under the Environmental Impact Assessment
Ordinance (EIAO). An Environmental Impact Assessment (EIA) Report (Report No.:
AEIAR-201/2016) for the Project was approved under EIAO in October 2016 in
accordance with the EIA Study Brief (No. ESB-276/2014) and the Technical
Memorandum on Environmental Impact Assessment Process (EIAO-TM). The
corresponding Environmental Permit was issued (EP no.: FEP-01/510/2016) by the
Director of Environmental Protection (DEP).
2.3 According to an approved
Environmental Monitoring and Audit (EM&A) Manual, an air quality and noise
monitoring programme is recommended during the construction phases of the
Project to monitor the expected dust and noise nuisances. Baseline air quality
and noise monitoring were conducted by previous ET (Wellab Limited) from 14th
March 2020 to 2nd April 2020 to establish the background conditions of the
designated sensitive receivers prior to the commencement of the Project’s
construction works.
2.4 The site layout plan for the
Project is shown in Figure 1.
Project Organization
2.5 Different
parties with different levels of involvement in the Project organization under
EP no.: FEP-01/510/2016 include:
Project Proponent – Architectural Services Department
(ArchSD)
Contractor– China State JV
Environmental Team (ET) – Ka Shing Management Consultancy
Ltd.
Independent Environmental Checker (IEC) – Acuity
Sustainability Consulting Limited
2.6 The
key personnel contact names and numbers under Quotation No.
PMB202/8480/2022/A01/A and the other contact names and numbers under ArchSD
Contract No. SSK509 are summarised in Table 2.1.
Table 2.1 Key
Contacts of the Project
Party |
Role |
Contact
Person |
Phone
No. |
Fax No. |
Architectural
Services Department |
Project Proponent |
Mr. Vincent Kwok |
2867 3939 |
3542 5223 |
Contractor (China State JV) |
Site Agent |
Mr. Kelvin Chan |
6272 8828 |
2866 6325 |
Environmental
Officer |
Ms. Marian Kong |
6174 9735 |
||
Mr. LuLu Mar |
5998 8852 |
|||
Ka Shing Management
Consultancy Ltd. |
ETL |
Mr. W.H. Lee |
2618 2166 |
2120 7752 |
Acuity
Sustainability Consulting Limited |
IEC |
Ir. Y.H. Law |
2698 6833 |
2698 9383 |
Summary of Construction Works Undertaken During Reporting
Quarter
2.7 The
major site activities undertaken in the reporting quarterly included:
l Open cut
excavation
l Removal of
soil
l Construction
of footings
l Mock-up
construction
l Construction
of substructure
l Construction
of footbridge
l Backfilling
l U.U. Lead in and Pipe Duct Connection
Status of Environmental Licences, Notifications and
Permits
2.8 A summary of the relevant permits,
licences, and/or notifications on environmental protection for this Project is
presented in Table 2.2
Table 2.2 Status
of Environmental Licences, Notifications and Permits
Permit / Licence No. |
Valid Period |
Status |
|
From |
To |
||
Further Environmental Permit (FEP) |
|||
FEP-01/510/2016 |
N/A |
N/A |
Valid |
Construction Noise Permit (CNP) |
|||
GW-RN0302-24 |
19-03-2024 |
18-06-2024 |
Cancelled |
GW-RN0483-24 |
30-04-2024 |
29-07-2024 |
Valid |
Notification pursuant to Air Pollution Control (Construction Dust)
Regulation |
|||
EPD Ref no.: 487864 |
N/A |
N/A |
N/A |
Billing Account for Construction Waste Disposal |
|||
Account
No. 7046289 |
18-01-2023 |
N/A |
Valid |
Registration of Chemical Waste Producer |
|||
WPN5213-641-C4770-01 |
18-01-2023 |
N/A |
Valid |
Effluent Discharge Licence under Water Pollution Control Ordinance |
|||
WT00043663-2023 |
21-04-2023 |
30-04-2028 |
Valid |
Summary of EM&A Requirement
2.9 The
EM&A programme requires construction noise monitoring, air quality
monitoring, ecological monitoring and environmental site audits. The EM&A
requirements are described in the following sections, including:
l
All monitoring parameters;
l
Action and Limit levels for all environmental
parameters;
l
Event / Action Plans;
l
Environmental mitigation measures, as
recommended in the Project EIA study final report; and
l
Environmental requirements in contract
documents.
3
ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENT
Monitoring Parameters and Monitoring Locations
Air Quality Monitoring
3.1 In
accordance with the EM&A Manual, impact 1-hour TSP monitoring was conducted
to monitor the air quality for the Works Contracts. The locations of the
monitoring stations are shown in Figure 2. Table 3.1 describes the
location of the air quality monitoring stations.
Table 3.1 Location for Air Quality Monitoring
Stations
Monitoring
Station |
Location
of Measurement |
AM1 |
Village House, Kong
Nga Po |
AM2 |
Village House, Kong
Nga Po |
3.2 Table 3.2 summarises the monitoring parameters and frequencies of impact air
quality monitoring during the Works Contracts activities.
Table 3.2 Impact Air Quality
Monitoring Parameters, Frequency and Duration
Parameters |
Frequency |
1-hr TSP |
Three times/ 6 days |
Noise Monitoring
3.3 In
accordance with the EM&A Manual, construction noise monitoring were conducted to monitor the construction noise arising
from the construction activities. The locations of the monitoring stations are
shown in Figure 3. Table 3.3 describes the location of the noise monitoring stations.
Table
3.3
Location of Noise Monitoring Stations
Monitoring
Station |
Location
of Measurement |
NM9 |
Village House, Kong
Nga Po |
NM10 |
Village House, Kong
Nga Po |
NM11 |
Village House, Kong
Nga Po |
NM12 |
Village House, Kong
Nga Po |
NM13 |
Village House, Kong
Nga Po |
NM14 |
Village House, near
Man Kam To Road |
3.4 Table 3.4 summarises the monitoring parameters and frequencies of construction
noise monitoring during the Works Contracts activities.
Table 3.4 Noise Monitoring Parameters,
Duration and Frequency
Monitoring
Stations |
Parameter |
Duration |
Frequency |
Measurement |
NM9 |
L10(30 min.) dB(A)[2] |
0700-1900 hrs on normal weekdays |
Once per week |
Free field[1] |
NM10 |
Free field[1] |
|||
NM11 |
Façade |
|||
NM12 |
Façade |
|||
NM13 |
Free field[1] |
|||
NM14 |
Free field[1] |
Remarks:
[1]: Correction of +3dB (A) for
Free-field Measurement.
[2]: A-weighted equivalent
continuous sound pressure level (Leq). It is the constant noise level which,
under a given situation and time period, contains the same acoustic energy as
the actual time-varying noise level.
L10 is the level exceeded for
10% of the time. For 10% of the time, the sound or noise has a sound pressure
level above L10.
L90 is the level exceeded for
90% of the time. For 90% of the time, the noise level is above this level.
Monitoring Methodology and Calibration
Details
3.5 Monitoring works/equipment were
conducted/calibrated regularly in accordance with the Project Specific EM&A
Manual. Copies of calibration certificates were attached in the relevant
Monthly EM&A Reports.
Environmental Quality Performance Limits
(Action and Limit Levels)
3.6 The environmental quality
performance limit i.e. Action and Limit Levels were derived from the baseline
monitoring results. Should the measured environmental quality parameters exceed
the Action/Limit Levels, the respective action plans would be implemented. The
Action/Limit Levels for each environmental parameter are given in Appendix A.
Landscape and visual
3.7 Bi-weekly inspection of the
implementation of landscape and visual mitigation measures was conducted during
weekly site audit. Most of the necessary mitigation measures have been
implemented and recommended follow-up actions have been discharged by the Contractor.
Details of the audit findings and implementation status are summarized in Appendix F and Appendix G.
Ecology Monitoring
3.8 Ecology monitoring was carried out
on a monthly basis to monitor the timely implementation of proper environmental
management practices and mitigation measures for the retained and transplanted
individuals of flora species of conservation interest. Proper erection and
maintenance of the temporary protective fence enclosing the individuals was
inspected for the effectiveness. The ecological monitoring photo records and
result could refer to the relevant Monthly EM&A Reports.
Site Audit Summary
3.9 Site audit were carried out on a
weekly basis to monitor and audit the timely implementation of proper
environmental management practices and mitigation measure of this Project. The
observations and recommendations made during the reporting period are summarized
in Appendix G.
Environmental Mitigation Measures
3.10 Relevant mitigation measures as
recommended in the project EIA report have been stipulated in the Project
EM&A Manual for the Contractor to implement. A summary of the Environmental
Mitigation Implementation Schedule (EMIS) is given in Appendix F.
Status of Waste Management
3.11 The amount of wastes generated by the
major site activities of this Project during the reporting quarter is shown in Appendix H.
4
MONITORING
RESULTS
Weather
Conditions
4.1 The detail of weather
conditions for each individual monitoring session could be referred to monthly
EM&A reports.
Air Quality
1-hr TSP Monitoring
4.2 All construction air quality monitoring was conducted as
scheduled during the reporting quarter.
4.3 No Action/Limit Level exceedance was
recorded in this reporting quarter. A summary of exceedance is attached in Appendix E.
4.4 Table 4.1
summarizes the air quality monitoring results which were extracted from the
monthly reports for this Project. The graphical presentation of the air quality
monitoring results is shown in Appendix
B.
Table 4.1 Summary of 1-hour TSP
Monitoring Result in Reporting Quarter
Reporting Months |
Air Quality
Monitoring Station |
Average |
Range |
Action Level |
Limit Level |
μg/m3 |
μg/m3 |
μg/m3 |
μg/m3 |
||
Apr-24 |
AM1 |
76 |
41 – 135 |
308 |
500 |
AM2 |
78 |
39 – 119 |
311 |
||
May-24 |
AM1 |
61 |
41 – 80 |
308 |
|
AM2 |
63 |
39 – 89 |
311 |
||
Jun-24 |
AM1 |
65 |
22 – 155 |
308 |
|
AM2 |
48 |
22 – 65 |
311 |
Construction
Noise
4.5 All construction noise monitoring
was conducted as scheduled in the reporting quarter.
4.6 No Action Level exceedance was
recorded in this reporting month. No Limit Level exceedance was recorded. A
summary of exceedance is attached in Appendix E.
4.7 Table 4.2 summarizes the
noise monitoring results which were extracted from the monthly reports for this
Project. The graphical presentations of the construction noise monitoring
results are shown in Appendix C.
Table 4.2 Summary of Noise Monitoring Result in
Reporting Quarter Remarks:
Reporting Months |
Noise Quality
Monitoring Station |
Average |
Range |
Baseline Level
dB(A) |
Limit Level,
dB(A) |
Leq (30
min), dB(A) |
Leq (30
min), dB(A) |
||||
Apr -24 |
NM9 |
63.4 |
58.5 – 68.7 |
55.9 |
75 |
NM10 |
56.6 |
47.5 – 66.8 |
52.8 |
||
NM11 |
56.1 |
46.7 – 65.0 |
46.4 |
||
NM12 |
49.6 |
40.8 – 53.7 |
54.7 |
||
NM13 |
59.0 |
50.2 – 69.2 |
61.3 |
||
NM14 |
52.3 |
46.9 – 59.2 |
59.6 |
||
May-24 |
NM9 |
54.8 |
44.1 – 64.8 |
55.9 |
|
NM10 |
55.1 |
49.9 – 65.0 |
52.8 |
||
NM11 |
53.6 |
46.9 – 60.1 |
46.4 |
||
NM12 |
53.5 |
48.2 – 60.4 |
54.7 |
||
NM13 |
55.5 |
52.0 – 60.0 |
61.3 |
||
NM14 |
48.4 |
41.8 – 57.2 |
59.6 |
||
Jun-24 |
NM9 |
56.3 |
51.2 – 64.9 |
55.9 |
|
NM10 |
52.7 |
49.3 – 62.5 |
52.8 |
||
NM11 |
54.7 |
47.2 – 64.5 |
46.4 |
||
NM12 |
58.2 |
47.5 – 70.4 |
54.7 |
||
NM13 |
55.5 |
39.7 – 62.8 |
61.3 |
||
NM14 |
59.8 |
45.5 – 74.3 |
59.6 |
Ecological
Monitoring
4.8 Monthly
monitoring of flora species of conservation interest were conducted by ET as
scheduled in the reporting quarter. No construction activity and equipment
storage were observed within the receptor site. Temporary protective fences
were found properly erected and maintained for the transplanted species.
4.9 According
to approved transplantation proposal, the post-transplantation monitoring for
transplanted Brainea insignis and Spiranthes sinensis was conducted
by Contractor post-transplantation monitoring on transplanted Brainea insignis
and Spiranthes
sinensis was conducted once per month by the Contractor under Contract No.
SSK509 from April to June 2024 during the reporting period.
4.10 The contractor provided
maintenance works including watering, use of mulch and weeding to allow healthy
growth of the transplanted species. The post-transplantation monitoring records
were submitted to ET and IEC for review and were included in the relevant
monthly EM&A Reports for record keeping.
5 ENVIRONMENTAL
SITE INSPECTION
Site Audits
5.1 Site
audits were carried out by ET on weekly basis in the reporting quarter to
monitor the timely implementation of proper environmental management practices
and mitigation measures on the project site. No non-conformance was identified
and the observation and recommendations made in each individual site audit
session in the reporting period are summarized in Appendix G.
Implementation
Status of Environmental Mitigation Measures
5.2 According
to the EIA Report, Environmental Permit and the EM&A Manual of the Project,
the mitigation measures detailed in the documents are recommended to be
implemented during the construction phase. An updated summary of the
Environmental Mitigation Implementation Schedule (EMIS) is provided in Appendix
F.
Solid and
Liquid Waste Management Status
5.3 In
accordance with the EM&A Manual, waste management was audited during weekly
site audit to determine if wastes are being managed in accordance with the
Waste Management Plan (WMP) prepared for the Project and the relevant
legislative and contractual requirements. Waste management practice including
waste handling, storage, transportation and disposal were audited.
5.4 The
Contractor is advised to minimize the wastes generated through the recycling or
reusing. All mitigation measures stipulated in the EM&A Manual and waste
management plans shall be fully implemented. The status of implementation of
waste management and reduction measures are summarised in Appendix F.
5.5 Waste
generated from this Project includes inert C&D materials and non-inert
C&D materials. Non-inert C&D materials are made up of general refuse
and waste that cannot be reused or recycled and has to be disposed of at the
designated landfill sites. The amount of wastes generated by the construction
works of the Project during the reporting quarter is shown in Appendix H.
6 NON-COMPLIANCE
(EXCEEDANCES) OF THE ENVIRONMENTAL QUALITY PERFORMANCE LIMITS (ACTION AND LIMIT
LEVELS)
Summary of
Exceedances
6.1 Environmental
monitoring works were performed in the reporting quarter and all monitoring
results were checked and reviewed. A summary of exceedance is attached in
Appendix E.
6.2 No
exceedance of Action/Limit Levels of air quality and construction noise was
recorded in the reporting quarter.
6.3 No
Action Level exceedance for noise monitoring was recorded. No exceedance of
Limit Level of construction noise was recorded in the reporting quarter.
Summary of
Environmental Non-Compliance
6.4 No
environmental non-compliance was recorded in the reporting quarter. The
observations and recommendations made in each individual site audit session
were presented in Appendix G.
Summary of
Environmental Complaint
6.5 One
complaint related to water quality was received in the reporting quarter. No
complaints related to air quality. The Cumulative Complaint Log since the
commencement of the Project is attached in Appendix
I.
Summary of
Environmental Summon and Successful Prosecution
6.6 There
was no successful environmental prosecution or notification of summons received
in the reporting quarter. The Cumulative Log for environmental summon and
successful prosecution since the commencement of the Project is presented in Appendix
J.
7 FUTURE
KEY ISSUES
Key Issues
in the Coming Three Months
7.1 The major
construction activities undertaken in the coming three months will include:
·
Open cut excavation
·
Removal of soil
·
Construction of footings
·
Construction of pile cap
·
Construction of substructure
·
Construction of footbridge
·
Backfilling
·
Mock up construction
·
U.U. Lead in and Pipe Duct Connection
7.2 Potential
environmental impacts arising from the above construction activities are mainly
associated with construction dust, noise, water quality, waste management and
ecology. The proactive Environmental Protection Proforma summarizing the major
site activities, potential environmental impacts and recommended mitigation
measures for the coming months could refer to relevant Monthly EM&A Report.
7.3 Dust
can be generated during construction works and exposed site area in the summer
months and windy weather in the upcoming dry season. To prevent high dust
concentrations during the summer months, the Contractor should pay attention on
the air quality mitigation measures as far as practicable to minimise the dust
impact to the villages which are located adjacent to the Project works. The
Contractor was also reminded to follow the Project Implementation Schedule in
approved EIA report / EM&A Manual to implement appropriate dust control to
reduce dust emissions from heavy construction activities (including ground
excavation, earth moving, etc.) at all active works area exposed site surfaces
and unpaved roads, particularly during dry weather and covering 80% of
stockpiling area by impervious sheets and spraying all dusty material with
water immediately prior to any loading transfer operations to keep the dusty
materials wet during material handling at the stockpile areas as well as the
relevant dust control practices as stipulated in the Air Pollution Control
(Construction Dust) Regulation so that no adverse dust impact arising from the
Project works site.
7.4 In
addition, construction noise is also one of the key environmental issues during
construction of the Project. Noise mitigation measures such as using quiet
plants and noise barriers should be in place, where applicable. In addition,
the Contractor was reminded to frequently check and maintain the acoustic
materials wrapped on noisy part of PME and ensure no gaps between noise
barriers; proactively identify any potential construction noise impact to NSRs
and provide sufficient mitigation measures if necessary; and provide
notification to nearby villagers in Kong Nga Po for potential noisy works at
works area.
7.5 All
other mitigation measures recommended in the Project Implementation Schedule in
approved EIA report / EM&A Manual should be properly implemented and
maintained as far as practicable.
8 CONCLUSIONS
AND RECOMMENDATIONS
Conclusions
8.1 This
Quarterly EM&A Report presents the EM&A work undertaken from April to
June 2024 in accordance with EM&A Manual.
8.2 Environmental
monitoring and audit works were performed in the reporting quarter and all
monitoring results were checked and reviewed.
Air
Quality Monitoring
8.3 Air Quality
monitoring was conducted as scheduled in the reporting quarter. No Action/Limit
Level exceedance was recorded.
Construction
Noise Monitoring
8.4 Construction
Noise monitoring was conducted as scheduled in the reporting quarter. No Limit
Level exceedance was recorded. No exceedance of Limit Level of construction
noise was recorded in the reporting quarter
Environmental
Site inspections
8.5 Environmental
site inspections were conducted as weekly basis in the reporting quarter. No
environmental non-compliance was recorded.
Environmental
Complaint and Successful Prosecution
8.6 One
complaint related to water quality was received in the reporting quarter. No
complaints related to air quality.
No notification of summons or successful prosecutions was received in
the reporting quarter.
Recommendations
8.7 The
mitigation measures recommended in the EIA report and EM&A Manual are
considered effective and efficient in minimizing environmental impacts due to
construction of the project during the reporting quarter. The EM&A
programme implemented by the ET has effectively monitored the environmental
impacts arising from the construction activities and ensure the proper
implementation of mitigation measures.
8.8 The
effectiveness and efficiency of the EM&A programme will be continuously
reviewed. The EM&A programme will be improved if deficiencies of the
existing EM&A programme are identified.
8.9 According
to the environmental audits performed in the reporting quarter, the following
recommendations were provided to remediate any potential impacts due to the
Project:
Air
Quality Impact
l To
maintain the cover for stockpile of dusty materials and exposed slope for dust
suppression;
l To enhance
the dust suppression measures including watering for the dust generation works,
exposed site area and haul road;
l To regular
check the valid NRMM labels are properly displayed on the regulated machines
and non-road vehicles; and
l To
maintain the wheel washing facilities provided at every construction site exit
where practicable are functioning properly.
Construction
Noise Impact
l To keep
inspect the noise sources inside the site;
l To keep
space out noisy equipment and position the equipment as far away as possible
from sensitive receivers; and
l To
maintain temporary noise barriers for operations of noisy equipment near the
noise sensitive receivers, if necessary.
Water
Impact
l To
maintain the cover for open stockpile of and exposed slope;
l To keep
reviewing and updating temporary drainage system;
l To
maintain the earth bunds or sand bag barriers on site to direct stormwater to
silt removal facilities;
l To
maintain and ensure the silt removal facilities are functioning properly;
l To
maintain the wheel washing facilities provided at every construction site exit
where practicable are functioning properly; and
l To divert
the muddy water at the retention pond to the wetsep for treatment before
discharging out.
Waste/Chemical
Management
l To check
for any accumulation of waste materials or rubbish on site;
l To avoid
any discharge or accidental spillage of chemical waste or oil directly from the
site;
l To
maintain the drip tray well to prevent oil and chemical leakage; and
l To avoid
improper handling, storage and dispose of oil drums or chemical containers on
site.
Ecology
l To erect
and maintain the protection fence around the retained trees / conservation
species;
l To keep
the tree protection zone large enough to protect the tress; and
l To remove
the construction materials within the tree protection zone.
Landscape and Visual
l To erect
and maintain the protection fencing and tree protection zone around the
preserved trees;
l To remove
the construction materials within the tree protection zone; and
l To keep
the tree protection zone large enough to protect the tress.