|
|
Page
No. |
|
EXECUTIVE SUMMARY |
|
|
Introduction |
5 |
|
Environmental
Monitoring and Audit Progress |
5 |
|
Breaches
of Action and Limit Levels |
5 |
|
Construction
Noise |
5 |
|
Air
Quality |
6 |
|
Ecological
Monitoring |
6 |
|
Environmental
Non-Compliance |
6 |
|
Environmental
Complaint |
6 |
|
Notification
of Summons and Successful Prosecutions |
6 |
|
Reporting
Changes |
6 |
|
Future
Key Issues |
6-7 |
|
|
|
INTRODUCTION |
|
|
|
Purpose
of the report |
8 |
|
Structure
of the report |
8 |
|
|
|
2 |
PROJECT
INFORMATION |
|
|
Background |
9 |
|
Project
Organization |
9-10 |
|
Summary
of Construction Works Undertaken During Reporting Month |
10 |
|
Construction
Programme |
10 |
|
Status
of Environmental Licences, Notifications and
Permits |
10-11 |
|
Summary
of EM&A Requirement |
11 |
|
Status
of Compliance with Environmental Permits Conditions |
11-12 |
|
|
|
3 |
NOISE
MONITORING |
|
|
Monitoring
Requirements |
13 |
|
Monitoring
Location |
13 |
|
Monitoring
Equipment |
13 |
|
Monitoring
Parameters, Frequency and Duration |
14 |
|
Monitoring
Methodology and QA/QC Procedures |
14-15 |
|
Maintenance
and Calibration |
15 |
|
Results
and Observations |
15-16 |
|
Event
and Action Plan |
16 |
|
|
|
4 |
AIR
QUALITY MONITORING |
|
|
Monitoring
Requirements |
17 |
|
Monitoring
Location |
17 |
|
Monitoring
Equipment |
17-18 |
|
Monitoring
Parameters, Frequency and Duration |
18 |
|
Monitoring
Methodology and QA/QC Procedure |
18-19 |
|
Results
and Observations |
19-20 |
|
Event
and Action Plan |
20 |
|
|
|
5 |
LANDSCAPE
AND VISUAL MONITORING |
|
|
Monitoring
Requirements |
21 |
|
|
|
6 |
ECOLOGICAL
MONITORING |
|
|
Monitoring
of Flora Species of Conservation Interest |
22 |
|
Post-Transplantation
Monitoring and Maintenance Programme |
22-23 |
|
Results
and Observations |
23-24 |
|
Precautionary
Measure for Butterfly Species of Conservation Interest |
24 |
|
Precautionary
Measures to Minimize Indirect Disturbance on Ecology |
24 |
|
|
|
7 |
ENVIRONMENTAL
SITE INSPECTION |
|
|
Site
Audits |
25 |
|
Implementation
Status of Environmental Mitigation Measures |
26 |
|
Solid
and Liquid Waste Management Status |
26 |
|
|
|
8 |
ENVIRONMENTAL
NON-CONFORMANCE |
|
|
Summary
of Exceedances |
27 |
|
Summary
of Environmental Non-Compliance |
27 |
|
Summary
of Environmental Complaint |
27 |
|
Summary
of Environmental Summon and Successful Prosecution |
27 |
|
|
|
9 |
FUTURE
KEY ISSUES |
|
|
Key
Issues in the Coming Three Months |
28-29 |
|
Monitoring
Schedule for the Next Month |
29 |
|
|
|
10 |
CONCLUSIONS
AND RECOMMENDATIONS |
|
|
Conclusions |
30 |
|
Recommendations |
30-31 |
LIST OF TABLES
Table I Summary
Table for EM&A Activities in the Reporting Month
Table II Summary
Table for Events Recorded in the Reporting Month
Table 2.1 Key
Contacts of the Project
Table 2.2 Status
of Environmental Licences, Notifications and Permits (Contract No. SSK509)
Table 2.3 Summary
Table for Status of Compliance / Required Submission
Table 3.1 Location
for Noise Monitoring Stations
Table 3.2 Noise
Monitoring Equipment
Table 3.3 Noise
Monitoring Parameters, Duration and Frequency
Table 3.4 Summary
Table of Noise Monitoring Results during the Reporting Month
Table 3.5 Observation
at Noise Monitoring Stations
Table 4.1 Location
for Air Quality Monitoring Locations
Table 4.2 Air
Quality Monitoring Equipment
Table 4.3 Impact
Dust Monitoring Parameters, Frequency and Duration
Table 4.4 Summary
Table of 1-hour TSP Monitoring Results during the Reporting Month
Table 4.5 Observation
at Dust Monitoring Stations
Table 7.1 Observations
and Recommendations of Site Audit
LIST OF FIGURES
Figure 1 Site
Layout Plan
Figure 2 Location
of Air Quality Monitoring Stations
Figure 3 Location
of Noise Monitoring Stations
LIST OF APPENDICES
Appendix A Construction
Programme and Proactive Environmental Protection Proforma
Appendix B Action
and Limit Levels
Appendix C Copies
of Calibration Certificates
Appendix D Environmental
Monitoring Schedules
Appendix E Air
Quality Monitoring Results and Graphical Presentation
Appendix F Noise
Monitoring Results and Graphical Presentation
Appendix G Weather
Condition
Appendix H Ecological
Monitoring Records
Appendix I Event
Action Plans
Appendix J Summary
of Exceedance
Appendix K Environmental
Mitigation Implementation Schedule (EMIS)
Appendix L Waste
Generation in the Reporting Month
Appendix M Complaint
Log
Appendix N Summary
of Successful Prosecution
Appendix O The
potential seriousness of the forthcoming environmental impacts and the use of
machineries
Appendix P A
List of Machineries Used in Construction Site
Appendix Q Wastewater
Discharge Layout Plan
EXECUTIVE SUMMARY
Introduction
E1. This document represents the 17th monthly report
detailing the Environmental Monitoring and Audit (EM&A) activities
for the Kong Nga Po Police Facilities Project, which operates under
Environmental Permit No. FEP-01/510/2016. This report was prepared by Ka Shing
Management Consultancy Ltd. (Ka Shing) under “Service Contract Quotation No.
PMB202/8480/2022/A01/A Provision of Environmental Team consultancy for Design
and Construction of Kong Nga Po Police Training Facilities” (hereinafter called
the “Service Contract”). The report encapsulates the EM&A activities and
findings carried out between the 1st and 31st of August 2024.
E2.
On the 23rd of December 2022, a section of the construction site was
transferred to the Architectural Services Department (ArchSD), which assumed
responsibility for the building's construction. Furthermore, ArchSD has taken
on the role of maintenance agent for the Hong Kong Police Force (HKPF)
throughout the operational phase.
E3.
In the month covered by this report, the Project of Police Facilities at Kong
Nga Po, which operates under Environmental Permit No. FEP-01/510/2016, engaged
in the following contractual work: Contract No. SSK509, which encompasses the
design and construction of the Kong Nga Po Police Training Facilities.
Environmental Monitoring and Audit Progress
E4. A
summary of the EM&A activities in this reporting month is listed in Table
I below:
Table I
Summary Table for EM&A Activities in the Reporting Month
EM&A Activities |
Date |
Noise Monitoring |
03, 09, 15, 21, 27 August 2024 |
Air Quality Monitoring |
03, 09, 15, 21, 27 August 2024 |
Environmental Site Inspection |
5, 13, 21, 27 August 2024 |
Ecological Monitoring |
27, 30 August 2024 |
Landscape & Visual Inspection |
5, 13, 21, 27 August 2024 |
Breaches of Action and Limit Levels
E5. Summary
of the environmental exceedances of the reporting month is tabulated in Table II.
Construction Noise
E6.
During the reporting month, the
planned noise monitoring for construction took place as scheduled, with no
recorded incidents of the Action/Limit Levels being exceeded.
Air Quality
E7. Throughout the reporting period,
all planned air quality monitoring associated with construction was executed,
and there were no recorded instances where the Action/Limit Levels were
surpassed.
Table II Summary Table for Events
Recorded in the Reporting Month
Environmental Monitoring |
Parameter |
No. of Non-Project related Exceedances |
No. of Exceedance related to the
Construction Works of the Contract |
Action Taken |
||
Action Level |
Limit Level |
Action Level |
Limit Level |
|||
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
N/A |
Air Quality |
1-hr TSP |
0 |
0 |
0 |
0 |
N/A |
Ecological Monitoring
E8. The ecological monitoring slated
for the reporting month was conducted according to schedule. Details of the
findings from this ecological monitoring for the respective period are
available in Appendix H.
Environmental Non-Compliance
E9. During
the reporting month, no environmental compliance violations were documented.
Environmental Complaint
E10. No environmental complaints were recorded during the reporting period. In
the event of any complaints, they would be documented in the Complaint Log
found in Appendix M.
Notification of Summons and Successful
Prosecutions
E11. Throughout the month covered in this report,
there were no instances of receiving notifications regarding summons or
confirmations of successful prosecutions.
Reporting Changes
E12. On the 23rd of December 2022, a section of the
construction site was handed over to the Architectural Services Department
(ArchSD). ArchSD has taken on the task of overseeing the construction
activities for the building. This Monthly Environmental Monitoring and Audit
(EM&A) Report offers a summary of the site operations and the status of the
environmental safeguards being implemented under the contract with ArchSD.
Future Key Issues
E13. The
major site activities for the coming three months include:
1. Open cut
excavation
2. Removal of soil
3. Construction of
footings
4. Construction of
substructure and superstructure
5. Construction of
footbridge
6. Backfilling
7. U.U. Lead in and
Pipe Duct Connection
8. MIC installation
E14. The aforementioned construction
activities could potentially lead to environmental impacts, with the primary
concerns centered around construction dust, noise, water quality, and waste
management. For detailed information, please refer to Appendix A regarding the anticipated major impacts from the
construction works and corresponding recommended mitigation measures.
1
INTRODUCTION
1.1 The Architectural Services Department (ASD)
has commissioned Ka Shing Management Consultancy Ltd. (Ka Shing) as the
Environmental Team (ET) to conduct the Environmental Monitoring and Audit
(EM&A) activities for the Kong Nga Po Police Facilities Project, as
dictated by Environmental Permit No. FEP-01/510/2016.
1.2 The main construction activities for the
Project began on the 3rd of July, 2020, and the primary location at Kong Nga Po
was handed over to the Architectural Services Department (ASD) on the 23rd of
December, 2022. The ASD has assumed control over the building construction
tasks and will serve as the maintenance representative for the Hong Kong Police
Force (HKPF) once the project is operational.
Purpose of the report
Structure
of the report
1.4 The structure of the report is as
follows:
Section 1: Introduction
Section
2: Project Information
Section 3: Noise Monitoring
Section
4: Air Quality Monitoring
Section
5: Landscape and Visual Monitoring
Section
6: Ecological Monitoring
Section
7: Environmental Site Inspection.
Section 8: Environmental Non-conformance
Section 9: Future Key Issues
Section 10:
Conclusions and Recommendations
2 PROJECT
INFORMATION
Background
2.1 The Project mainly includes
construction and operation of various police facilities. The police
facilities include:
(i) a helipad;
(ii) two
firing ranges; and
(iii) other
facilities, associated infrastructure & utilities, etc.
2.2 The Project falls under the category of a
Designated Project as defined by the Environmental Impact Assessment Ordinance
(EIAO). In October 2016, an Environmental Impact Assessment (EIA) Report
(Report No.: AEIAR-201/2016) was approved for the Project in accordance with
the EIA Study Brief (No. ESB-276/2014) and the Technical Memorandum on
Environmental Impact Assessment Process (EIAO-TM). The corresponding
Environmental Permit (EP no.: FEP-01/510/2016) was issued by the Director of
Environmental Protection (DEP).
2.3 As per the approved Environmental
Monitoring and Audit (EM&A) Manual, a comprehensive air quality and noise
monitoring program is recommended during the construction phases of the Project
to assess and monitor potential dust and noise nuisances. Prior to the
commencement of the Project's construction works, baseline air quality and
noise monitoring were conducted by the previous Environmental Team (Wellab
Limited) from 14th March, 2020, to 2nd April, 2020, to establish the
pre-existing conditions at designated sensitive receivers.
2.4 Figure 1 displays the site layout plan
for the Project.
Project Organization
2.5 Various stakeholders with varying
degrees of participation are part of the Project's organizational structure
under Environmental Permit number: FEP-01/510/2016, which includes:
Project Proponent
– Architectural Services Department (ArchSD)
Contractor– China
State JV
Environmental
Team (ET) – Ka Shing Management Consultancy Ltd.
Independent
Environmental Checker (IEC) – Acuity Sustainability Consulting Limited
2.6 Table 2.1 summarizes the
contact information for key personnel associated with Quotation No.
PMB202/8480/2022/A01/A and additional contacts linked with the ArchSD Contract
No. SSK509.
Table 2.1 Key
Contacts of the Project
Party |
Role |
Contact Person |
Phone No. |
Fax No. |
Architectural Services Department |
Project Proponent |
Mr. Vincent Kwok |
2867 3939 |
3542 5223 |
Contractor (China State JV) |
Site Agent |
Mr. Kelvin Chan |
6272 8828 |
2866 6325 |
Environmental Officer |
Ms. Marian Kong |
6174 9735 |
||
Mr. LuLu Mar |
5998 8852 |
|||
Ka Shing Management Consultancy Ltd. |
ETL |
Mr. W.H. Lee |
2618 2166 |
2120 7752 |
Acuity Sustainability Consulting Limited |
IEC |
Ir. Y.H. Law |
2698 6833 |
2698 9383 |
Summary of Construction Works Undertaken
During Reporting Month
2.7 Significant
site activities conducted on-site during the reporting month comprised:
1. Open cut excavation
2. Removal of soil
3. Construction of footings
4. Construction of substructure and superstructure
5. Construction of footbridge
6. Backfilling
7. U.U. Lead in and Pipe Duct Connection
Construction Programme
2.8 Appendix A contains a version of the
Contractors' construction schedules. The primary site activities planned by the
Contractor for the upcoming three months have been examined. In Appendix O, the expected environmental
impacts' potential severity and the deployment of equipment have been
evaluated. This appendix additionally provides the Contractor with
recommendations and insights on alternative approaches aimed at raising
environmental consciousness, refining practices on the construction site, and
fostering environmental improvements.
2.9 Table 2.2 presents a
consolidated overview of the pertinent environmental protection permits,
licenses, and/or notifications associated with this Project.
Table 2.2 Status
of Environmental Licences, Notifications and Permits
Permit / Licence No. |
Valid
Period |
Status |
|
From |
To |
||
Further Environmental Permit (FEP) |
|||
FEP-01/510/2016 |
N/A |
N/A |
Valid |
Construction Noise Permit (CNP) |
|||
GW-RN0839-24 |
30-07-2024 |
29-10-2024 |
Valid |
Notification pursuant to Air Pollution Control
(Construction Dust) Regulation |
|||
EPD Ref no.: 487864 |
N/A |
N/A |
N/A |
Billing Account for Construction Waste Disposal |
|||
Account No. 7046289 |
18-01-2023 |
N/A |
Valid |
Registration of Chemical Waste Producer |
|||
WPN5213-641-C4770-01 |
18-01-2023 |
N/A |
Valid |
Effluent Discharge Licence under Water Pollution
Control Ordinance |
|||
WT00043663-2023 |
21-04-2023 |
30-04-2028 |
Valid |
Summary of EM&A Requirement
2.10 The Environmental Monitoring and Audit
(EM&A) program includes the monitoring of construction noise, air quality,
ecological conditions, and regular environmental site audits. The specific
requirements for the EM&A program are outlined in the following sections:
l Environmental requirements in contract
documents;
l Event / Action Plans;
l Environmental mitigation measures, as
recommended in the Project EIA study final report;
l All monitoring parameters; and
l Action and Limit levels for all
environmental parameters.
Status of Compliance with Environmental
Permits Conditions
2.11 Table 2.3 provides a summary of the
adherence to Environmental Permit (EP) No. FEP-01/510/2016 and the necessary
submissions connected to this Project as stipulated by the EP.
Table 2.3 Summary
Table for Status of Compliance / Required Submission under FEP No. FEP-01/510/2016
FEP Conditions |
Submission |
Submission Date |
Approval Status |
1.12 |
Commencement
date of construction of
the Project |
30/3/2023 |
* |
2.7 |
Proposal on the
Reporting Mechanism and Curriculum Vitae of the IEC |
20/3/2023 |
* |
2.10 |
The date of
setting up the Community Liaison Hotline and the contact details |
27/2/2023 |
* |
2.11 |
Management
Organization of Main
Construction Companies, at
least an organization chart, names of responsible
persons and their contact
details |
10/3/2023 |
* |
2.12 |
Construction
Works Schedule and Location Plans |
10/3/2023 |
* |
2.13 |
Layout plan for
permeable pavings |
29/3/2023 Supplementary information submitted on 23/3/2024 |
For approval |
2.14 |
Landscape and
visual mitigation plan |
26/6/2023 |
For approval |
2.16 |
Plan for perimeter
walls/ boundary wall sat project site and sidewalls of firing range |
1 month before fence wall works |
For approval |
2.19 |
Submission of
Helicopter Flight Plan |
1 month before commencement of operation of Helipad |
Notification |
3.3 |
Baseline Air
Quality and Noise Monitoring Report |
30/3/2023 |
Deposit |
4.2 |
Internet address
of a dedicated web site |
13/4/2023 |
* |
Remarks:
* Approval not required in FEP-01/510/2016
3 NOISE
MONITORING
Monitoring Requirements
3.1 Following
the EM&A Manual, monitoring of construction noise was performed by
measuring the A-weighted equivalent continuous sound pressure level (Leq) to
track noise generated by construction operations. Each monitoring station is
scheduled for weekly noise assessments, with one set of readings to be taken
from 0700 to 1900 hours on typical weekdays. The predefined Action/Limit Levels
for the environmental monitoring activities are presented in Appendix B.
Monitoring Location
3.2 As per Section 3.2.3 of the
EM&A Manual, impact noise monitoring took place at fourteen specified noise
monitoring stations. Following the guidelines of the Project's Environmental
Impact Assessment (EIA) report, noise monitoring stations situated within a
300-meter radius of the Project's boundary were taken into account.
Consequently, six noise monitoring stations identified as relevant monitoring
locations are depicted in Figure 3. The specific locations of these noise
monitoring stations are detailed in Table 3.1.
Table 3.1
Location of Noise Monitoring Stations
Monitoring Station |
Location of Measurement |
NM9 |
Village House, Kong Nga Po |
NM10 |
Village House, Kong Nga Po |
NM11 |
Village House, Kong Nga Po |
NM12 |
Village House, Kong Nga Po |
NM13 |
Village House, Kong Nga Po |
NM14 |
Village House, near Man Kam To Road |
Monitoring
Equipment
3.3 Impact noise monitoring was carried
out using Integrating Sound Level Meters. These meters, classified as Type 1,
are capable of providing continuous readings of noise levels, including the
equivalent continuous sound pressure level (Leq) and percentile sound pressure
level (Lx), and they conform to the specifications of International
Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type
1). The noise monitoring equipment utilized is summarized in Table 3.2.
The calibration certificates for these devices can be found in Appendix C.
Table 3.2 Noise Monitoring Equipment
Equipment |
Model |
Quantity |
Sound Level Meter |
BSWA 308 |
1 |
Sound Calibrator |
ST120 |
1 |
Monitoring
Parameters, Frequency and Duration
3.4 Table 3.3 encapsulates the variables
monitored, the frequency of monitoring, and the total time span of the noise
monitoring activities. The schedule for noise monitoring can be located in
Appendix D.
Table 3.3 Noise Monitoring Parameters, Duration and
Frequency
Monitoring Stations |
Parameter |
Duration |
Frequency |
Measurement |
NM9 |
L10(30 min.) dB(A)[2] |
0700-1900 hrs on normal
weekdays |
Once per week |
Free field[1] |
NM10 |
Free field[1] |
|||
NM11 |
Façade |
|||
NM12 |
Façade |
|||
NM13 |
Free field[1] |
|||
NM14 |
Free field[1] |
Remarks:
[1]: Correction of +3dB (A) for Free-field
Measurement.
[2]: A-weighted equivalent continuous sound
pressure level (Leq). It is the constant noise level which, under a given
situation and time period, contains the same acoustic energy as the actual
time-varying noise level.
L10 is the level exceeded for 10% of the
time. For 10% of the time, the sound or noise has a sound pressure level above
L10.
L90 is the level exceeded for 90% of the
time. For 90% of the time, the noise level is above this level.
Monitoring
Methodology and QA/QC Procedures
3.5 The
procedures for noise monitoring were conducted in this manner:
- The sound level
meter was mounted on a tripod, positioned 1 meter away from the outside of the
noise-sensitive facade and at a height of 1.2 meters above ground level;
- To achieve free
field measurement conditions, the meter was placed at a distance from any
reflective surfaces, and the measured noise levels were then corrected by
adding +3 dB(A);
-
The battery's condition was examined to guarantee the proper operation of the
meter;
- The settings for
parameters like frequency weighting, time weighting, and measurement duration
were established as detailed below:
-frequency weighting: A
-time weighting: Fast
-time measurement: Leq(30 min.) dB(A)
- Noise levels were
measured as six consecutive Leq, 5-minute readings during the hours when
restrictions did not apply (specifically, from 0700 to 1900 hrs
on normal weekdays).
- Calibration of
the meter was performed before and after each noise measurement session using a
Calibrator set to 94.0 dB at 1000 Hz. Should there be a discrepancy greater
than 1.0 dB in calibration levels pre- and post-measurement, the data would be
deemed invalid. A repeat measurement would then be necessary following
recalibration or repair of the equipment.
- Throughout the
monitoring period, parameters such as Leq, L90, and L10 were documented.
Observations regarding site conditions and noise origins were also noted on a
standard recording form.
- Noise
measurements were temporarily halted during instances of significant intrusive
noise (for example, barking dogs or helicopter sounds), where feasible. An
observation record for the measurement period was to be provided.
- Noise monitoring
was suspended in conditions of fog, rain, or when wind speeds were consistently
above 5 m/s, or during gusts surpassing 10 m/s. Wind speeds were verified using
a portable anemometer capable of measuring speed in meters per second (m/s).
Maintenance and
Calibration
3.6 Every three months, the microphone
head of the sound level meter and the calibrator was gently wiped clean using a
soft fabric.
3.7 Annually the sound level meter and
calibrator underwent inspection and calibration.
3.8 Before and after conducting each
noise measurement, the precision of the sound level meter
must be verified with an acoustic calibrator that produces a set sound
pressure level at a specific frequency. Only when the pre- and post-measurement
calibration levels are within a 1.0 dB range of each other will the
measurements be considered valid.
Results and
Observations
3.9 Table 3.4 provides a summary
of the noise monitoring outcomes. For an in-depth account and visual depiction
of the noise monitoring, refer to Appendix F. A summary of the
meteorological data for the reporting period is compiled in Appendix G.
Table 3.4
Summary Table of Noise Monitoring Results during the Reporting Month
Monitoring Station |
Average |
Range |
Baseline Level |
Limit Level |
Leq (30 min) dB(A) |
Leq (30 min) dB(A) |
dB(A) |
dB(A) |
|
NM9[1] |
52.9 |
47.6 – 67.9 |
55.9 |
75 |
NM10[1] |
53.0 |
48.7 – 73.8 |
52.8 |
|
NM11 |
51.9 |
48.0 – 63.9 |
46.4 |
|
NM12 |
58.0 |
50.1 – 70.1 |
54.7 |
|
NM13[1] |
52.2 |
47.2 – 59.9 |
61.3 |
|
NM14[1] |
57.8 |
47.6 – 73.0 |
59.6 |
Remarks: [1]:
Correction of +3dB (A) for Free-field Measurement.
3.10 Noise monitoring
related to construction activities took place according to the planned schedule
for the month reported. There were no instances where the Action/Limit Levels
were surpassed. A summary of exceedance records for the reporting month can be found
in Appendix J.
3.11 Based on observations
made in the field, the primary sources of noise detected at the allocated noise
monitoring stations during the reporting month are as outlined below:
Table 3.5 Observation at Noise Monitoring Stations
Monitoring Station |
Major Noise Source |
NM9 |
Loading & unloading, Road traffic, Excavation
works |
NM10 |
Loading & unloading, Road traffic, Excavation
works |
NM11 |
Road traffic |
NM12 |
Loading & unloading, Road traffic |
NM13 |
Loading & unloading, Road traffic |
NM14 |
Dog barking, Road traffic |
Event and Action
Plan
3.12 If any non-compliance
with the criteria related to the project arises, measures will be taken
following the procedures outlined in the Event Action Plan provided in Appendix I.
4 AIR
QUALITY MONITORING
Monitoring Requirements
4.1 As per the EM&A Manual, 1-hour
Total Suspended Particulates (TSP) monitoring was carried out to keep track of
the air quality associated with the Works Contracts. The predetermined
Action/Limit Levels for the air quality monitoring activities are detailed in Appendix B.
4.2
Monitoring for 1-hour Total
Suspended Particulates (TSP) impacts was performed at a minimum of three times
within each six-day period at a designated air quality monitoring station.
Monitoring Location
4.3 In line with Section 2.2.5 of the
EM&A Manual, impact air quality monitoring took place at two specified
monitoring stations for the Project, as depicted in Figure 2. The positions of
the air quality monitoring stations are detailed in Table 4.1.
Table 4.1 Location for Air
Quality Monitoring Stations
Monitoring Station |
Location of Measurement |
AM1 |
Village House, Kong Nga Po |
AM2 |
Village House, Kong Nga Po |
Monitoring Equipment
4.4 Due to the denial by local
villagers to set up a High-Volume Sampler (HVS) for 1-hour Total Suspended
Particulates (TSP) monitoring at the chosen locations and the inability to
secure an electricity supply for the HVS, direct-reading dust meters were utilized
instead to conduct the 1-hour TSP monitoring. Direct-reading dust meters are
widely accepted instruments for measuring 1-hour TSP levels and have been used
in the same infrastructure project. The issue to use direct-reading dust meters
was presented to the Independent Environmental Checker (IEC). The application
of the direct-reading dust meter allows for immediate and straightforward
results, facilitating timely EM&A reporting and the execution of the event
and action plan. To ensure the validity and accuracy of the readings obtained
by the direct-reading method, the HVS performed 1-hour sampling on a bi-monthly
schedule.
4.5 Table 4.2 provides a summary of the apparatus employed
in the impact air quality monitoring program. Copies of the calibration
certificates for the equipment can be found in Appendix C.
Table 4.2 Air
Quality Monitoring Equipment
Equipment |
Model and Serial No. |
Quantity |
The valid period is until |
Dust Monitor |
AEROCET-831 / E11304 |
1 |
21 August 2024 |
Dust Monitor |
AEROCET-831 / D12641 |
1 |
19 October 2024 |
4.6 Weather
data was sourced from the "Hong Kong Observatory - General Weather
Conditions during the Monitoring Period (August 2024)" detailed in Appendix
G, which was used as a substitute approach to acquire representative wind
data.
4.7 During the monitoring days, the field staff also
documented the prevailing weather conditions, such as whether it was sunny,
cloudy, or rainy.
Monitoring Parameters, Frequency and Duration
4.8 Table
4.3 encapsulates the
monitoring variables and the regularity of impact dust assessments conducted
throughout the Works Contracts operations. The schedule for air quality
observation for the month in question is presented in Appendix D.
Table 4.3 Impact
Dust Monitoring Parameters, Frequency and Duration
Parameters |
Frequency |
1-hr TSP |
Three times/ 6 days |
Monitoring
Methodology and QA/QC Procedure
1-hour
TSP Air Quality Monitoring
Instrumentation
4.9 The air quality monitoring
utilized a direct reading dust meter, as indicated in Table 4.2.
4.10 The procedures for operating the dust meter
adhere to the guidelines set forth in the Manufacturer’s Instruction Manual, as
described below:
-The 1-hour dust meter is placed at least
1.3 meters above ground.
-Press and hold the Power key momentarily
to power on the unit and make sure that the battery level was not flash or in
low level.
-Allow the instrument to stand for about 3
second to display the Sample Screen minutes.
-Press the START / STOP key to run the
internal vacuum pump for 1 minute and ready to use.
-Use the select dial to select the PM range
and press the START / STOP key to start a measurement.
-Finally, push the START/STOP key to stop
the measuring after 3-hour sampling.
-Information such as sampling date, time,
value and site condition were recorded during the monitoring period.
-All data were recorded in the data logger
for further data processing.
Maintenance/Calibration
4.11 The dust meter required
the following maintenance and calibration:
- The dust meter
must be checked and calibrated against a High Volume Sampler (HVS) to validate
the precision and accuracy of the readings obtained through the direct reading
method. This calibration should be performed bi-monthly during all phases of
the air quality monitoring.
- The correlation
between the dust meter and HVS in measuring TSP was established by directly
comparing the mass of dust particles collected on a filter paper by the HVS
against the dust meter's reading. For accurate calibration, both the dust meter
and the HVS should be turned on and off at the same location and at the same
time.
- The correlation
coefficient was verified to confirm the relationship between the readings from
the dust meter and the HVS. This correlation factor was ascertained by
comparing the outcomes from both the HVS and the dust meter.
- Prior to the
initiation of dust monitoring, a check must be conducted to verify that all
equipment is operational and has the necessary power supply. A zero count test
was performed before and after each monitoring session to ensure accuracy.
Results and
Observations
4.12 The outcomes of the
1-hour TSP monitoring are condensed in Table 4.4. For a comprehensive
view, detailed results and graphical representations of the 1-hour TSP
monitoring data can be found in Appendix
E.
Table 4.4
Summary Table of 1-hour TSP Monitoring Results during the Reporting
Month
Monitoring Station |
Concentration |
Action Level, μg/m3 |
Limit Level, μg/m3 |
|
(μg/m3) |
||||
Average |
Range |
|||
AM1 |
45 |
19 – 75 |
308 |
500 |
AM2 |
39 |
24 – 63 |
311 |
4.13 The 1-hour TSP
monitoring took place according to the planned timetable for the reporting
month, and there were no instances of exceeding the established Action/Limit
Levels.
4.14 Based
on field observations, the primary sources of dust at the specified air quality
monitoring stations during the reporting month are listed in Table 4.5.
Table 4.5 Observation at Dust
Monitoring Stations
Monitoring Station |
Major Dust Source |
AM1 |
Equipment
operation and movement / road traffic, exposed site area, site vehicle |
AM2 |
Road traffic,
exposed site area, site vehicle / equipment operation and movement, vehicle /
equipment operation and movement at warehouse nearby |
Event and Action
Plan
4.15 In
the event of a project-related violation of the criteria, measures will be
taken as specified by the Event Action Plan detailed in Appendix I.
5 LANDSCAPE
AND VISUAL MONITORING
Monitoring
Requirements
5.1 The EIA Report recommends implementing strategies to
mitigate impacts on landscape and visual resources throughout
both the construction and operational phases of the Project.
5.2 The execution and upkeep of
compensatory planting for landscaping are critical components of this process
and must be monitored to confirm their complete fulfillment. It is essential to
promptly address any potential clashes between the proposed landscaping efforts
and other Project tasks or operational needs to ensure that the mitigation
measures' objectives are not compromised. Furthermore, the enforcement of the
mitigation measures advised by the EIA will be tracked continuously through the
site audit program for the construction phase.
5.3 The Environmental Team (ET) carried
out a fortnightly review of the execution of measures aimed at mitigating
landscape and visual impacts as part of the weekly site audits. The findings
and observations from these audit sessions are encapsulated in Table 7.1,
while the status of implementation can be found detailed in Appendix K.
6 ECOLOGICAL
MONITORING
Monitoring of
Flora Species of Conservation Interest
6.1 In line
with Section 8.3.2 of the EM&A Manual, a temporary protective barrier must
be installed around the plant species of conservation significance identified
in the detailed vegetation survey throughout the construction phase. This
barrier should be well-maintained and regularly checked to ensure its
effectiveness. Monthly checks of each plant species of conservation interest,
as pinpointed in the detailed vegetation survey, are required during the
construction phase to ensure that these species remain unaffected by the
project's construction activities.
6.2 The
monitoring aims to oversee the prompt execution of suitable environmental
management practices and the application of mitigation measures concerning the
preserved and relocated specimens of flora species of conservation interest.
The correct setup and upkeep of the temporary protective fence surrounding
these specimens were examined to assess its efficacy. The protective measures
outlined in the approved transplantation proposal's implementation schedule
were supervised.
6.3 As per the
sanctioned detailed vegetation survey report and transplantation proposal, it
was determined that 71 Brainea insignis specimens, 41 Spiranthes sinensis specimens, and 3 Aquilaria sinensis specimens should be
relocated to the designated receiving site. Additionally, it was decided to
preserve in situ 51 Keteleeria fortunei
specimens, along with 26 small seedlings of Keteleeria fortunei and 7 small seedlings of Aquilaria sinensis, in the vicinity of
Kong Nga Po Road near the Police Dog Unit and the Force Search Unit Training
School.
Post-Transplantation
Monitoring and Maintenance Programme
6.4 In line
with the accepted transplantation proposal, the Contractor is mandated to carry
out post-transplantation monitoring weekly for the first three months, and then
monthly for the remainder of the 12-month establishment phase as well as the
subsequent post-establishment phase, continuing until the construction phase of
the Project concludes. This routine monitoring is critical for promptly
identifying the growth condition of the transplanted species, any signs of
construction work within or in the vicinity of the receptor site, and any
changes in the environmental conditions of the receptor site.
6.5 For
the initial year of acclimatization, it was advised to carry out maintenance
activities to promote the robust growth of the transplanted species.
Considering the state of the transplanted organisms following the 12-month
establishment period, it was advised that maintenance activities continue
through the Post-establishment Period until the completion of the Construction
Phase. It was recommended to water the transplants daily for the first three
months following the move, as well as throughout periods of drought, to
maintain soil moisture. Additional maintenance tasks, such as mulching and
weeding, should be performed as necessary.
Results and
Observations
6.6 During
the reporting month, the Contractor carried out monthly evaluations of the
flora species of conservation interest on the 30th of August 2024. The
enforcement of the protective measures detailed in the approved transplantation
proposal was reviewed, along with the maintenance of the temporary protective
fencing. Appendix H contains the
photographic documentation and checklists from the monthly assessments. The
health of the transplanted and retained species was generally observed to be
average to poor. The Contractor was urged to keep a vigilant eye on the
transplanted species and to implement the protective measures as specified in
the approved transplantation proposal to safeguard these species. Furthermore,
the Contractor was given the following directives:
1)
To provide new identification tags for any Brainea insignis that were missing them;
2)
To substitute any plant labels at the receptor site that had become illegible
due to fading;
3)
To refer to the soil improvement guidelines published by the Greening,
Landscape and Tree Management Section (GLTMS) of the Development Bureau (2022)
for application in the monitoring and upkeep of the transplanted plant species;
4)
To set up shade nets;
5)
To ensure the soil remains moist by adhering to the necessary daily watering
schedule.
Transplanted Brainea insignis and Spiranthes
sinensis
6.7 From
May 21st to 27th, 2020, 71 Brainea insignis
specimens and 41 Spiranthes sinensis specimens were relocated to
the receptor site. The detailed account of the transplantation process was
compiled in a Transplantation Report and forwarded to ET(Wellab), IEC(Acuity),
and the Supervisor (AECOM) for their examination and documentation. Monitoring
after transplantation took place weekly for the initial three months (from June
to August 2020) and then monthly throughout the subsequent 12-month
establishment period, as well as the post-establishment phase, culminating with
the conclusion of the construction phase of the Project. The Contractor was
responsible for tracking the health of the transplanted species and carried out
maintenance measures such as watering, mulching, and weeding during the first
year to nurture the transplanted species' healthy development. Monitoring of
the transplanted Brainea insignis and Spiranthes sinensis took place on August 30th, 2024, within the reporting
period, with the findings documented in Appendix
H. Particular attention was given to the transplanted Brainea insignis specimens that were impacted by a bushfire on February
2nd, 2021, with their progress detailed in the post-transplantation monitoring
records. The health of the preserved species was noted to be generally fair.
The Contractor was advised to maintain vigilant monitoring of these species and
to enforce the stipulated protective measures to ensure their continued preservation.
6.8 During the
monthly checks, it was observed that there were no construction operations or
storage of equipment taking place within the receptor site. The temporary
protective barrier had been correctly installed and was being well-maintained
to safeguard the transplanted species.
Precautionary
Measure for Butterfly Species of Conservation Interest
6.9
As
stipulated by FEP Condition 2.17, to reduce the impact on butterfly species of
conservation concern, efforts shall be made to improve the new grassland
habitats within the Project site. This enhancement shall be achieved by
cultivating suitable plant species that serve as the larval food source for
butterflies of conservation interest, like the Small Three-Ring, thereby
supporting the well-being of these species.
6.10
The
restoration of grassland zones within the Project must be completed prior to
the initiation of the Project's operational phase. Information regarding the
plant species to be used as larval food plants for butterflies, along with the
design and execution details, will be subsequently provided under the building
works contract of ArchSD.
Precautionary
Measures to Minimize Indirect Disturbance on Ecology
6.11
As
outlined in Section 9.7.3 of the EIA Report, implementing mitigation strategies
for air, noise, water, waste, and landscaping can serve as preventative actions
to avert and lessen any secondary effects of disturbance or pollution resulting
from construction activities on the surrounding ecology and habitats outside
the site. The Environmental Team (ET) conducted weekly site audits to oversee
the prompt adoption of appropriate environmental management practices and the
execution of mitigation measures at the Project site. The findings from these
audits are consolidated in Section 7.3.
7 ENVIRONMENTAL
SITE INSPECTION
Site Audits
7.1 The Environmental Team (ET)
conducted site audits weekly to oversee the prompt adoption of appropriate
environmental management practices and the execution of mitigation measures at
the Contract site.
7.2 The Environmental Team (ET), along
with representatives from the Client and the Contractor, conducted site audits
on 5, 13, 21, 27 August 2024 of the reported month in 2024.
7.3 In the site inspections conducted over
the reporting period, there were no particular environmental concerns noted. It
should be recognized that these observations pertain solely to the moments of
inspection. The findings and advice from these audits are compiled in Table
7.1. The absence of identified environmental issues during the joint site
inspections does not exempt the Contractor from their obligation to adhere
strictly to all legal requirements, the Particular Specifications, and the
Environmental Monitoring and Audit (EM&A) Manual.
Table 7.1 Observations
of Weekly site Inspection and advice
Parameters |
Date |
Observations |
Advice |
Water Quality Impact |
21-8-2024 |
The labelling (particulars on the label)
and storage of chemicals should be in accordance with the Code of Practice on
the Packaging, Labelling and Storage of Chemical Wastes and maintained at all
times by the Contractor |
Particulars on the label are shown on the chemical. |
Water Quality Impact |
21-8-2024 |
The labelling |
The symbol of the
chemicals is clearly visible |
Others |
21-8-2024 |
The absence of a drip tray may elevate the
risk of rainwater or cleaning activities carrying spilled chemicals into the
surrounding soil. This contamination not only has the potential to hinder
plant growth but also poses a probable threat to the local ecosystem. These
chemical substances can disrupt the delicate balance, harming or even proving
fatal to beneficial microorganisms |
The drip tray should be used. |
Implementation
Status of Environmental Mitigation Measures
7.4
In
accordance with the EIA Report and the Project's EM&A Manual, the outlined
mitigation measures are recommended to be implemented throughout the
construction phase. An overview of the Environmental Mitigation Implementation
Schedule (EMIS) is available in Appendix
K.
Solid and Liquid Waste Management Status
7.5 Pursuant to
the EM&A Manual, waste management practices were reviewed in the weekly
site audits to assess compliance with the Project's Waste Management Plan (WMP)
and pertinent legal and contractual obligations. The auditing process
encompassed the examination of waste handling, storage, transport, and disposal
methods.
7.6 The
Contractor has appointed Environmental Officers on-site to manage environmental
aspects, implement pollution control strategies, maintain proper site conduct,
and educate workers on waste management. Efforts to reduce waste production
include actively using Construction and Demolition (C&D) materials.
Excavated materials have been sorted and screened on-site to salvage any
recyclables. Non-reactive C&D materials were utilized on-site for backfill
and to construct the haul road surface. Furthermore, inert materials from
excavation activities were repurposed as fill in other local projects. Excess
inert C&D materials were sent to the Government’s public fill reception
facilities (PFRFs) for use in other projects. To oversee the disposal of inert
and non-inert C&D materials and prevent illegal dumping, a system is in
place where all materials are weighed by a weighbridge before leaving the site,
and the Trip Ticket System is rigorously enforced.
7.7 Contractor
is encouraged to reduce waste production by recycling or reusing materials. It
is imperative that all the mitigation strategies outlined in the EM&A
Manual and the waste management plans be thoroughly executed. A summary of the
progress in implementing waste management and reduction strategies is provided
in Appendix K.
7.8 This
Project produces inert Construction and Demolition (C&D) materials as well
as non-inert C&D materials. The non-inert variety consists of general
refuse and other waste materials that cannot be repurposed or recycled,
necessitating disposal at assigned landfill locations. Data detailing the
volume of waste resulting from the Project's construction activities over the
reporting period can be found in Appendix
L.
8 ENVIRONMENTAL
NON-CONFORMANCE
Summary of
Exceedances
8.1 During the
reporting month, there were no instances where the air quality exceeded the
established Action and Limit Levels.
8.2 There were
no instances of construction noise surpassing the designated Action and Limit
Levels in the reporting period.
8.3 If the
monitoring data from any specific stations reveal that environmental parameters
have surpassed the Action/Limit Levels, then the procedures outlined in the
Event and Action Plans in Appendix I
should be executed. A summary of any exceedance records for the reporting month
can be found in Appendix J.
Summary of
Environmental Non-Compliance
8.4 There were
no records of environmental compliance breaches during the reported month.
Summary of
Environmental Complaint
8.5 In the month under review, no complaints
were registered. A log of all complaints accumulated since the start of the
Project is compiled in Appendix M.
Summary of
Environmental Summon and Successful Prosecution
8.6 Since the
beginning of the Project, there have been no instances of successful
environmental prosecution or receipt of summons. A comprehensive record of all
environmental summonses and successful prosecutions since the Project's
inception is documented in Appendix N.
9 FUTURE
KEY ISSUES
Key Issues in the Coming Three Months
9.1 Appendix A contains the provisional
construction schedules for the Project. Over the next three months, the
principal construction tasks to be carried out will include:
1.
Open cut excavation
2. Removal
of soil
3. Construction
of footings
4. Construction
of substructure and superstructure
5. Construction
of footbridge
6. Backfilling
7. U.U.
Lead in and Pipe Duct Connection
8.
MIC installation
9.2 Referring
to the site layout plan found in Appendix
A, which details the expected construction activities for the next three
months, the primary environmental concerns related to these activities are
likely to be construction dust, noise, water quality, waste management,
landscape and visual aesthetics, and ecological impacts. The anticipated
environmental effects have been factored into the mitigation strategies planned
for the upcoming months.
9.3 The
Contractor has advised mitigation measures for the next three months, which the
Environmental Team (ET), Independent Environmental Checker (IEC), and the
Client's Representative have reviewed through email correspondence during site
audits. The Proactive Environmental Protection Proforma, which outlines the key
site activities, potential environmental impacts, and advised mitigation
strategies, has been examined and verified by the IEC and is displayed in Appendix A.
9.4 During
construction and in periods of dry weather, dust can arise from work activities
and uncovered site areas. To mitigate dust emissions that could affect nearby
villages, the Contractor is advised to diligently apply air quality control
measures as outlined in the layout plan in Appendix
A, to the greatest extent possible. Moreover, the Contractor is reminded to
adhere to the Project Implementation Schedule detailed in the approved EIA
report/EM&A Manual, implementing suitable dust suppression tactics to curb
emissions from intensive construction tasks such as ground excavation and earth
moving. This includes managing all active work areas, bare site surfaces, and
unpaved roads, especially under dry conditions, by covering 80% of stockpiled
materials with impervious coverings and by moistening dusty substances with
water just before loading and transfer activities. This ensures materials
remain damp during handling in stockpile regions. Additionally, the Contractor
must adhere to the prescribed dust control methods under the Air Pollution
Control (Construction Dust) Regulation to prevent negative dust impacts from
the Project's construction activities.
9.5 Furthermore,
construction noise represents a significant environmental concern during the
Project's development. It is important to implement noise reduction strategies,
such as utilizing quiet machinery and installing noise barriers where relevant.
The Contractor has been prompted to regularly inspect and upkeep the
sound-dampening materials on noisy sections of plant and machinery, ensuring
there are no openings in the noise barriers. They should also actively
recognize any potential construction noise impacts to Noise Sensitive Receivers
(NSRs) and introduce adequate mitigation measures when required. Additionally,
residents in the nearby Kong Nga Po village should be informed in advance about
any potentially noisy activities at the work site.
9.6 The
Contractor is advised to uphold measures that protect water quality throughout
the construction process. This includes constructing barriers such as dikes or
embankments to prevent flooding around the perimeters of areas where soil is
being moved or excavated. Provision should be made for temporary channels to
direct runoff effectively into a designated watercourse via a trap designed to
capture sediment from the site. These sediment/silt traps should also be
integrated into the permanent drainage systems to improve the settling of
particulates. It is essential to utilize effective silt removal systems to
ensure that the effluent treated by the wastewater treatment plant complies
with the standards specified in the WPCO licenses. The Wastewater Discharge
Layout Plan, as shown in Appendix Q and provided by the Contractor,
outlines the specific pathways through which wastewater is to be conveyed from
its source to a treatment facility or point of discharge
Monitoring Schedule for the Next Month
9.7 Appendix D displays the provisional
schedule for environmental monitoring activities planned for the upcoming
month.
10 CONCLUSIONS
AND RECOMMENDATIONS
Conclusions
10.1 This
Monthly EM&A Report details the environmental monitoring and audit
(EM&A) activities conducted in August 2024, following the guidelines set
out in the EM&A Manual.
10.2 During the month in question, air quality
monitoring did not register any instances of surpassing the Action/Limit Levels.
10.3 No instances of construction
noise exceeding the established Action/Limit Levels were documented in the
reporting month's monitoring records.
10.4 Site
inspections focusing on environmental aspects took place on the 5, 13, 21, 27
August 2024. Additionally, monitoring of landscape and visual impacts was
performed on the 5, 13, 21, 27 August 2024, and ecological monitoring was
conducted on the 27 August 2024 by ET within the reporting month. The
Contractor also conducted monitoring on 30 August 2024. There were no records
of environmental non-compliance for the reporting month. It should be noted
that the absence of any particular environmental issues during the joint site
inspections does not exempt the Contractor from their obligation to adhere
fully to all legal requirements, the specifications outlined in the contract,
and the procedures in the EM&A Manual.
10.5 During the reporting month, there were no
complaints lodged, nor were there any notices of summons or records of
successful legal actions received.
10.6
The Environmental Team
(ET) will persist in overseeing the Environmental Monitoring and Audit
(EM&A) program. All environmental obligations are fulfilled, and the
necessary mitigation measures are properly executed.
Recommendations
10.7 Based on the
environmental audits conducted during the reporting month, the subsequent
advice was put forward:
Air
Quality Impact
l
To
enhance the dust suppression measures including watering for the dust
generation works, exposed site area and haul road;
l
To
minimize the indirect impacts on air quality resulting from the operation of
machineries on the construction site, one of the measures to be adopted is the
use of biodiesel B100; and
l
To
regular check the valid NRMM labels are properly displayed on the regulated
machines and non-road vehicles
Construction
Noise
l
To
refer to the ISO 12001:1996 or other comprehensive practices and subsequently
develop a thorough inspection and maintenance protocol for the plant and
equipment, maintaining a focus on Noise Control; and
l
To
maintain temporary noise barriers for operations of noisy equipment near the
noise sensitive receivers, if necessary.
Water
Impact
l
To
maintain the cover for open stockpile of and exposed slope;
l
To
keep reviewing and updating temporary drainage system;
l
To
maintain the earth bunds or sand bag barriers on site to direct stormwater to
silt removal facilities; and
l
To
divert the muddy water at the retention pond to the wetsep for treatment before
discharging out.
Waste/Chemical
Management
l
To
check for any accumulation of waste materials or rubbish on site; and
l
To
avoid improper handling, storage and dispose of oil drums or chemical
containers on site.
Ecology
l
To
maintain soil moisture, daily watering is required;
l
To
install a shaded net;
l
To refer
to the Guidelines on Soil Improvement issued by the Greening, Landscape and
Tree Management Section (GLTMS) of the Development Bureau (2022) for the effective
monitoring and maintenance of transplanted flora species; and
l
The
wild plants that are growing in undesirable areas should be removed, as they
compete with the cultivated flora species of conservation interest.
Landscape
and Visual
l
To
remove the construction materials within the tree protection zone; and
l
To
keep the tree protection zone large enough to protect the tress.