EXECUTIVE SUMMARY |
|
|
Introduction |
4 |
|
Summary of Construction Works undertaken during the Reporting Quarter |
4 |
|
Environmental Monitoring and Audit Works |
4-5 |
|
Air Quality |
5 |
|
Construction Noise |
5 |
|
Ecological Monitoring |
5 |
|
Environmental Non-Compliance |
5 |
|
Environmental Complaint |
5 |
|
Notification of Summons and Successful Prosecutions |
5 |
|
Future Key Issues |
5-6 |
|
|
|
1 |
INTRODUCTION |
|
|
Purpose of the report |
7 |
|
Structure of the report |
7 |
|
|
|
2 |
PROJECT INFORMATION |
|
|
Background |
8 |
|
Project Organization |
8-9 |
|
Summary of Construction Works Undertaken During Reporting Quarter |
9 |
|
Status of Environmental Licences, Notifications and Permits |
9-10 |
|
Summary of EM&A Requirement |
10 |
|
|
|
3 |
ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENT |
|
|
Monitoring Parameters and Monitoring Locations |
11-12 |
|
Monitoring Methodology and Calibration Details |
12 |
|
Environmental Quality Performance Limits (Action and Limit Levels) |
12 |
|
Landscape and visual |
12 |
|
Ecology Monitoring |
12-13 |
|
Site Audit Summary |
13 |
|
Environmental Mitigation Measures |
13 |
|
Status of Waste Management |
13 |
|
|
|
4 |
MONITORING RESULTS |
14 |
|
Weather Conditions |
14 |
|
Air Quality |
14 |
|
Construction Noise |
14-15 |
|
Ecological Monitoring |
15 |
|
|
|
|
|
|
5 |
ENVIRONMENTAL SITE INSPECTION |
|
|
Site Audits |
16 |
|
Implementation Status of Environmental Mitigation Measures |
16 |
|
Solid and Liquid Waste Management Status |
16 |
|
|
|
6 |
NON-COMPLIANCE (EXCEEDANCES) OF THE ENVIRONMENTAL |
|
|
QUALITY PERFORMANCE LIMITS (ACTION AND LIMIT LEVELS) |
|
|
Summary of Exceedances |
17 |
|
Summary of Environmental Non-Compliance |
17 |
|
Summary of Environmental Complaint |
17 |
|
Summary of Environmental Summon and Successful Prosecution |
17 |
|
|
|
7 |
FUTURE KEY ISSUES |
|
|
Key Issues in the Coming Three Months |
18-19 |
|
|
|
8 |
CONCLUSIONS AND RECOMMENDATIONS |
|
|
Conclusions |
20 |
|
Recommendations |
20-22 |
LIST OF TABLES |
|
Table I |
Summary Table for Events Recorded in the Reporting Quarter |
Table 2.1 |
Key Contacts of the Project |
Table 2.2 |
Status of Environmental Licences, Notifications and Permits |
Table 3.1 |
Location for Air Quality Monitoring Stations |
Table 3.2 |
Impact Air Quality Monitoring Parameters, Frequency and Duration |
Table 3.3 |
Location of Noise Monitoring Stations |
Table 3.4 |
Noise Monitoring Parameters, Duration and Frequency |
Table 4.1 |
Summary of 1-hour TSP Monitoring Result in Reporting Quarter |
Table 4.2 |
Summary of Noise Monitoring Result in Reporting Quarter |
|
|
LIST OF FIGURES |
|
Figure 1 |
|
Figure 2 |
|
Figure 3 |
|
|
|
LIST OF APPENDICES |
|
Appendix A |
|
Appendix B |
|
Appendix C |
|
Appendix D |
|
Appendix E |
|
Appendix F |
|
Appendix G |
|
Appendix H |
|
Appendix I |
|
Appendix J |
EXECUTIVE SUMMARY
Introduction
Contract No. SSK509 - Design and Construction of Kong Nga Po Police Training Facilities
Summary of Construction Works undertaken during the Reporting Quarter
Open cut excavation
Removal of soil
Construction of footings
Mock-up construction
Plate load test
Construction of substructure
Construction of footbridge
Environmental Monitoring and Audit Works
Table I Summary Table for Events Recorded in the Reporting Quarter
Environmental Monitoring |
Parameter |
No. of Non-Project related Exceedances |
No. of Exceedance related to the Construction Works of the Contract |
Action Taken |
||
Action Level |
Limit Level |
Action Level |
Limit Level |
|||
Air Quality |
1-hr TSP |
0 |
0 |
0 |
0 |
N/A |
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
N/A |
Air Quality
6. All construction air quality monitoring was conducted as scheduled in the reporting quarter. No Action/Limit Level exceedance was recorded in the reporting quarter.
Construction Noise
7. All Construction noise monitoring was conducted as scheduled in the reporting quarter. No Action/Limit Level exceedance was recorded in the reporting quarter.
Ecological Monitoring
8. All ecological monitoring was conducted as scheduled in the reporting quarter. The ecological monitoring photo records and results were shown in the relevant Monthly EM&A Reports.
Environmental Non-Compliance
9. No environmental non-compliance was recorded in the reporting quarter.
Environmental Complaint
10. No environmental complaint was received in the reporting quarter. The Complaint Log is presented in Appendix I.
Notification of Summons and Successful Prosecutions
11. No notification of summons or successful environmental prosecutions was received in the reporting quarter.
Future Key Issues
12. The major site activities for the coming three months include:
Open cut excavation
Removal of soil
Construction of footings
Construction of pile cap
Construction of substructure
Construction of footbridge
Mock up construction
U.U. Lead in and Pipe Duct Connection
13. Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, noise, water quality and waste management. The anticipated major impacts from the construction works and corresponding recommended mitigation measures are detailed in Appendix G of Site Audit Summary.
1 INTRODUCTION
Purpose of the report
Structure of the report
Section 1: Introduction - purpose and structure of the report.
Section 2: Project Information – summarises background and scope of the Project,
site description, project organisation and contact details, construction programme, the construction works undertaken and the status of Environmental Permits/Licences during the reporting period.
Section 3: Environmental Monitoring and Audit Requirement – summarises monitoring location and parameters, monitoring programmes, monitoring frequencies, Action and Limit Levels, Event / Action Plans, and Site Audit inspection.
Section 4: Monitoring Result – summarises the monitoring results in the reporting quarter.
Section 5: Environmental Site Inspection – summarises the audit findings of the weekly site inspections undertaken within the reporting period.
Section 6: Non-Compliance of the Environmental Quality Performance Limits (Action and Limit) – summarises any monitoring exceedance, environmental complaints, environmental summons and successful prosecutions within the reporting period.
Section 7: Future Key Issues – summarises the impact forecast and monitoring schedule for the next three months.
Section 8: Conclusions and Recommendations
Background
2.1 The Project mainly includes construction and operation of various police facilities. The police facilities include:
(i) a helipad;
(ii) two firing ranges; and
(iii) other facilities, associated infrastructure & utilities, etc.
2.2 The Project is a Designated Project under the Environmental Impact Assessment Ordinance (EIAO). An Environmental Impact Assessment (EIA) Report (Report No.: AEIAR-201/2016) for the Project was approved under EIAO in October 2016 in accordance with the EIA Study Brief (No. ESB-276/2014) and the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM). The corresponding Environmental Permit was issued (EP no.: FEP-01/510/2016) by the Director of Environmental Protection (DEP).
2.3 According to an approved Environmental Monitoring and Audit (EM&A) Manual, an air quality and noise monitoring programme is recommended during the construction phases of the Project to monitor the expected dust and noise nuisances. Baseline air quality and noise monitoring were conducted by previous ET (Wellab Limited) from 14th March 2020 to 2nd April 2020 to establish the background conditions of the designated sensitive receivers prior to the commencement of the Project’s construction works.
2.4 The site layout plan for the Project is shown in Figure 1.
Project Organization
2.5 Different parties with different levels of involvement in the Project organization under EP no.: FEP-01/510/2016 include:
Project Proponent – Architectural Services Department (ArchSD)
Contractor– China State JV
Environmental Team (ET) – Ka Shing Management Consultancy Ltd.
Independent Environmental Checker (IEC) – Acuity Sustainability Consulting Limited
2.6 The key personnel contact names and numbers under Quotation No. PMB202/8480/2022/A01/A and the other contact names and numbers under ArchSD Contract No. SSK509 are summarised in Table 2.1.
Table 2.1 Key Contacts of the Project
Party |
Role |
Contact Person |
Phone No. |
Fax No. |
Architectural Services Department |
Project Proponent |
Mr. Vincent Kwok |
2867 3939 |
3542 5223 |
Contractor (China State JV) |
Site Agent |
Mr. Kelvin Chan |
6272 8828 |
2866 6325 |
Environmental Officer |
Ms. Marian Kong |
6174 9735 |
||
Mr. LuLu Mar |
5998 8852 |
|||
Ka Shing Management Consultancy Ltd. |
ETL |
Mr. W.H. Lee |
2618 2166 |
2120 7752 |
Acuity Sustainability Consulting Limited |
IEC |
Ir. Y.H. Law |
2698 6833 |
2698 9383 |
Summary of Construction Works Undertaken During Reporting Quarter
2.7 The major site activities undertaken in the reporting quarterly included:
Open cut excavation
Removal of soil
Construction of footings
Mock-up construction
Plate load test
Construction of substructure
Construction of footbridge
Status of Environmental Licences, Notifications and Permits
2.8 A summary of the relevant permits, licences, and/or notifications on environmental protection for this Project is presented in Table 2.2
Table 2.2 Status of Environmental Licences, Notifications and Permits
Permit / Licence No. |
Valid Period |
Status |
|
From |
To |
||
Further Environmental Permit (FEP) |
|||
FEP-01/510/2016 |
N/A |
N/A |
Valid |
Construction Noise Permit (CNP) |
|||
GW-RN1337-23 |
20-12-2023 |
19-03-2024 |
Expired |
GW-RN0302-24 |
19-03-2024 |
18-06-2024 |
Valid |
Notification pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
EPD Ref no.: 487864 |
N/A |
N/A |
N/A |
Billing Account for Construction Waste Disposal |
|||
Account No. 7046289 |
18-01-2023 |
N/A |
Valid |
Registration of Chemical Waste Producer |
|||
WPN5213-641-C4770-01 |
18-01-2023 |
N/A |
Valid |
Effluent Discharge Licence under Water Pollution Control Ordinance |
|||
WT00043663-2023 |
21-04-2023 |
30-04-2028 |
Valid |
Summary of EM&A Requirement
2.9 The EM&A programme requires construction noise monitoring, air quality monitoring, ecological monitoring and environmental site audits. The EM&A requirements are described in the following sections, including:
All monitoring parameters;
Action and Limit levels for all environmental parameters;
Event / Action Plans;
Environmental mitigation measures, as recommended in the Project EIA study final report; and
Environmental requirements in contract documents.
Monitoring Parameters and Monitoring Locations
Air Quality Monitoring
3.1 In accordance with the EM&A Manual, impact 1-hour TSP monitoring was conducted to monitor the air quality for the Works Contracts. The locations of the monitoring stations are shown in Figure 2. Table 3.1 describes the location of the air quality monitoring stations.
Table 3.1 Location for Air Quality Monitoring Stations
Monitoring Station |
Location of Measurement |
AM1 |
Village House, Kong Nga Po |
AM2 |
Village House, Kong Nga Po |
3.2 Table 3.2 summarises the monitoring parameters and frequencies of impact air quality monitoring during the Works Contracts activities.
Table 3.2 Impact Air Quality Monitoring Parameters, Frequency and Duration
Parameters |
Frequency |
1-hr TSP |
Three times/ 6 days |
Noise Monitoring
3.3 In accordance with the EM&A Manual, construction noise monitoring were conducted to monitor the construction noise arising from the construction activities. The locations of the monitoring stations are shown in Figure 3. Table 3.3 describes the location of the noise monitoring stations.
Table 3.3 Location of Noise Monitoring Stations
Monitoring Station |
Location of Measurement |
NM9 |
Village House, Kong Nga Po |
NM10 |
Village House, Kong Nga Po |
NM11 |
Village House, Kong Nga Po |
NM12 |
Village House, Kong Nga Po |
NM13 |
Village House, Kong Nga Po |
NM14 |
Village House, near Man Kam To Road |
3.4 Table 3.4 summarises the monitoring parameters and frequencies of construction noise monitoring during the Works Contracts activities.
Table 3.4 Noise Monitoring Parameters, Duration and Frequency
Monitoring Stations |
Parameter |
Duration |
Frequency |
Measurement |
NM9 |
L10(30 min.) dB(A)[2] |
0700-1900 hrs on normal weekdays |
Once per week |
Free field[1] |
NM10 |
Free field[1] |
|||
NM11 |
Façade |
|||
NM12 |
Façade |
|||
NM13 |
Free field[1] |
|||
NM14 |
Free field[1] |
Remarks:
[1]: Correction of +3dB (A) for Free-field Measurement.
[2]: A-weighted equivalent continuous sound pressure level (Leq). It is the constant noise level which, under a given situation and time period, contains the same acoustic energy as the actual time-varying noise level.
L10 is the level exceeded for 10% of the time. For 10% of the time, the sound or noise has a sound pressure level above L10.
L90 is the level exceeded for 90% of the time. For 90% of the time, the noise level is above this level.
Monitoring Methodology and Calibration Details
3.5 Monitoring works/equipment were conducted/calibrated regularly in accordance with the Project Specific EM&A Manual. Copies of calibration certificates were attached in the relevant Monthly EM&A Reports.
Environmental Quality Performance Limits (Action and Limit Levels)
3.6 The environmental quality performance limit i.e. Action and Limit Levels were derived from the baseline monitoring results. Should the measured environmental quality parameters exceed the Action/Limit Levels, the respective action plans would be implemented. The Action/Limit Levels for each environmental parameter are given in Appendix A.
Landscape and visual
3.7 Bi-weekly inspection of the implementation of landscape and visual mitigation measures was conducted during weekly site audit. Most of the necessary mitigation measures have been implemented and recommended follow-up actions have been discharged by the Contractor. Details of the audit findings and implementation status are summarized in Appendix F and Appendix G.
Ecology Monitoring
3.8 Ecology monitoring was carried out on a monthly basis to monitor the timely implementation of proper environmental management practices and mitigation measures for the retained and transplanted individuals of flora species of conservation interest. Proper erection and maintenance of the temporary protective fence enclosing the individuals was inspected for the effectiveness. The ecological monitoring photo records and result could refer to the relevant Monthly EM&A Reports.
Site Audit Summary
3.9 Site audit were carried out on a weekly basis to monitor and audit the timely implementation of proper environmental management practices and mitigation measure of this Project. The observations and recommendations made during the reporting period are summarized in Appendix G.
Environmental Mitigation Measures
3.10 Relevant mitigation measures as recommended in the project EIA report have been stipulated in the Project EM&A Manual for the Contractor to implement. A summary of the Environmental Mitigation Implementation Schedule (EMIS) is given in Appendix F.
Status of Waste Management
3.11 The amount of wastes generated by the major site activities of this Project during the reporting quarter is shown in Appendix H.
Weather Conditions
Air Quality
1-hr TSP Monitoring
4.2 All construction air quality monitoring was conducted as scheduled during the reporting quarter.
4.3 No Action/Limit Level exceedance was recorded in this reporting quarter. A summary of exceedance is attached in Appendix E.
4.4 Table 4.1 summarizes the air quality monitoring results which were extracted from the monthly reports for this Project. The graphical presentation of the air quality monitoring results is shown in Appendix B.
Table 4.1 Summary of 1-hour TSP Monitoring Result in Reporting Quarter
Air Quality Monitoring Station |
Average |
Range |
Action Level |
Limit Level |
|
µg/m3 |
µg/m3 |
µg/m3 |
µg/m3 |
||
Jan-24 |
AM1 |
75 |
53 – 106 |
308 |
500 |
AM2 |
88 |
64 – 104 |
311 |
||
Feb-24 |
AM1 |
73 |
63 – 80 |
308 |
|
AM2 |
78 |
72 – 86 |
311 |
||
Mar-24 |
AM1 |
66 |
55 – 72 |
308 |
|
AM2 |
70 |
58 – 80 |
311 |
Construction Noise
4.5 All construction noise monitoring was conducted as scheduled in the reporting quarter.
4.6 No Action Level exceedance was recorded in this reporting month. No Limit Level exceedance was recorded. A summary of exceedance is attached in Appendix E.
4.7 Table 4.2 summarizes the noise monitoring results which were extracted from the monthly reports for this Project. The graphical presentations of the construction noise monitoring results are shown in Appendix C.
Table 4.2 Summary of Noise Monitoring Result in Reporting Quarter Remarks:
Reporting Months |
Noise Quality Monitoring Station |
Average |
Range |
Baseline Level dB(A) |
Limit Level, dB(A) |
Leq (30 min), dB(A) |
Leq (30 min), dB(A) |
||||
Jan-24 |
NM9 |
56.6 |
49.0 – 64.7 |
55.9 |
75 |
NM10 |
52.7 |
45.4 – 57.2 |
52.8 |
||
NM11 |
46.6 |
39.9 – 63.0 |
46.4 |
||
NM12 |
44.0 |
39.4 – 47.3 |
54.7 |
||
NM13 |
52.5 |
46.1 – 62.0 |
61.3 |
||
NM14 |
44.1 |
40.1 – 51.4 |
59.6 |
||
Feb-24 |
NM9 |
58.3 |
57.3 – 59.9 |
55.9 |
|
NM10 |
54.4 |
51.6 – 58.1 |
52.8 |
||
NM11 |
45.8 |
42.7 – 49.0 |
46.4 |
||
NM12 |
44.9 |
41.7 – 48.2 |
54.7 |
||
NM13 |
55.3 |
52.4 – 63.3 |
61.3 |
||
NM14 |
43.0 |
41.0 – 48.5 |
59.6 |
||
Mar-24
|
NM9 |
57.9 |
49.9 – 62.7 |
55.9 |
|
NM10 |
58.4 |
55.0 – 62.5 |
52.8 |
||
NM11 |
49.5 |
44.1 – 62.2 |
46.4 |
||
NM12 |
48.0 |
43.8 – 51.4 |
54.7 |
||
NM13 |
56.2 |
47.9 – 65.7 |
61.3 |
||
NM14 |
44.9 |
42.8 – 49.7 |
59.6 |
Ecological Monitoring
4.8 Monthly monitoring of flora species of conservation interest were conducted by ET as scheduled in the reporting quarter. No construction activity and equipment storage were observed within the receptor site. Temporary protective fences were found properly erected and maintained for the transplanted species.
4.9 According to approved transplantation proposal, the post-transplantation monitoring for transplanted Brainea insignis and Spiranthes sinensis was conducted by Contractor post-transplantation monitoring on transplanted Brainea insignis and Spiranthes sinensis was conducted once per month by the Contractor under Contract No. SSK509 from January to March 2024 during the reporting period.
4.10 The contractor provided maintenance works including watering, use of mulch and weeding to allow healthy growth of the transplanted species. The post-transplantation monitoring records were submitted to ET and IEC for review and were included in the relevant monthly EM&A Reports for record keeping.
Site Audits
5.1 Site audits were carried out by ET on weekly basis in the reporting quarter to monitor the timely implementation of proper environmental management practices and mitigation measures on the project site. No non-conformance was identified and the observation and recommendations made in each individual site audit session in the reporting period are summarized in Appendix G.
Implementation Status of Environmental Mitigation Measures
5.2 According to the EIA Report, Environmental Permit and the EM&A Manual of the Project, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase. An updated summary of the Environmental Mitigation Implementation Schedule (EMIS) is provided in Appendix F.
Solid and Liquid Waste Management Status
5.3 In accordance with the EM&A Manual, waste management was audited during weekly site audit to determine if wastes are being managed in accordance with the Waste Management Plan (WMP) prepared for the Project and the relevant legislative and contractual requirements. Waste management practice including waste handling, storage, transportation and disposal were audited.
5.4 The Contractor is advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in the EM&A Manual and waste management plans shall be fully implemented. The status of implementation of waste management and reduction measures are summarised in Appendix F.
5.5 Waste generated from this Project includes inert C&D materials and non-inert C&D materials. Non-inert C&D materials are made up of general refuse and waste that cannot be reused or recycled and has to be disposed of at the designated landfill sites. The amount of wastes generated by the construction works of the Project during the reporting quarter is shown in Appendix H.
6 NON-COMPLIANCE (EXCEEDANCES) OF THE ENVIRONMENTAL QUALITY PERFORMANCE LIMITS (ACTION AND LIMIT LEVELS)
Summary of Exceedances
6.1 Environmental monitoring works were performed in the reporting quarter and all monitoring results were checked and reviewed. A summary of exceedance is attached in Appendix E.
6.2 No exceedance of Action/Limit Levels of air quality and construction noise was recorded in the reporting quarter.
6.3 No Action Level exceedance for noise monitoring was recorded. No exceedance of Limit Level of construction noise was recorded in the reporting quarter.
Summary of Environmental Non-Compliance
6.4 No environmental non-compliance was recorded in the reporting quarter. The observations and recommendations made in each individual site audit session were presented in Appendix G.
Summary of Environmental Complaint
6.5 No environmental complaint was received in the reporting quarter. The Cumulative Complaint Log since the commencement of the Project is attached in Appendix I.
Summary of Environmental Summon and Successful Prosecution
6.6 There was no successful environmental prosecution or notification of summons received in the reporting quarter. The Cumulative Log for environmental summon and successful prosecution since the commencement of the Project is presented in Appendix J.
7 FUTURE KEY ISSUES
Key Issues in the Coming Three Months
7.1 The major construction activities undertaken in the coming three months will include:
Open cut excavation
Removal of soil
Construction of footings
Construction of pile cap
Construction of substructure
Construction of footbridge
Mock up construction
U.U. Lead in and Pipe Duct Connection
7.2 Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, noise, water quality, waste management and ecology. The proactive Environmental Protection Proforma summarizing the major site activities, potential environmental impacts and recommended mitigation measures for the coming months could refer to relevant Monthly EM&A Report.
7.3 Dust can be generated during construction works and exposed site area in the summer months and windy weather in the upcoming dry season. To prevent high dust concentrations during the summer months, the Contractor should pay attention on the air quality mitigation measures as far as practicable to minimise the dust impact to the villages which are located adjacent to the Project works. The Contractor was also reminded to follow the Project Implementation Schedule in approved EIA report / EM&A Manual to implement appropriate dust control to reduce dust emissions from heavy construction activities (including ground excavation, earth moving, etc.) at all active works area exposed site surfaces and unpaved roads, particularly during dry weather and covering 80% of stockpiling area by impervious sheets and spraying all dusty material with water immediately prior to any loading transfer operations to keep the dusty materials wet during material handling at the stockpile areas as well as the relevant dust control practices as stipulated in the Air Pollution Control (Construction Dust) Regulation so that no adverse dust impact arising from the Project works site.
7.4 In addition, construction noise is also one of the key environmental issues during construction of the Project. Noise mitigation measures such as using quiet plants and noise barriers should be in place, where applicable. In addition, the Contractor was reminded to frequently check and maintain the acoustic materials wrapped on noisy part of PME and ensure no gaps between noise barriers; proactively identify any potential construction noise impact to NSRs and provide sufficient mitigation measures if necessary; and provide notification to nearby villagers in Kong Nga Po for potential noisy works at works area.
7.5 All other mitigation measures recommended in the Project Implementation Schedule in approved EIA report / EM&A Manual should be properly implemented and maintained as far as practicable.
8 CONCLUSIONS AND RECOMMENDATIONS
Conclusions
8.1 This Quarterly EM&A Report presents the EM&A work undertaken from January to March 2024 in accordance with EM&A Manual.
8.2 Environmental monitoring and audit works were performed in the reporting quarter and all monitoring results were checked and reviewed.
Air Quality Monitoring
8.3 Air Quality monitoring was conducted as scheduled in the reporting quarter. No Action/Limit Level exceedance was recorded.
Construction Noise Monitoring
8.4 Construction Noise monitoring was conducted as scheduled in the reporting quarter. No Limit Level exceedance was recorded. No exceedance of Limit Level of construction noise was recorded in the reporting quarter
Environmental Site inspections
8.5 Environmental site inspections were conducted as weekly basis in the reporting quarter. No environmental non-compliance was recorded.
Environmental Complaint and Successful Prosecution
8.6 No environmental complaint was received in the reporting quarter. No notification of summons or successful prosecutions was received in the reporting quarter.
Recommendations
8.7 The mitigation measures recommended in the EIA report and EM&A Manual are considered effective and efficient in minimizing environmental impacts due to construction of the project during the reporting quarter. The EM&A programme implemented by the ET has effectively monitored the environmental impacts arising from the construction activities and ensure the proper implementation of mitigation measures.
8.8 The effectiveness and efficiency of the EM&A programme will be continuously reviewed. The EM&A programme will be improved if deficiencies of the existing EM&A programme are identified.
8.9 According to the environmental audits performed in the reporting quarter, the following recommendations were provided to remediate any potential impacts due to the Project:
Air Quality Impact
To maintain the cover for stockpile of dusty materials and exposed slope for dust suppression;
To enhance the dust suppression measures including watering for the dust generation works, exposed site area and haul road;
To regular check the valid NRMM labels are properly displayed on the regulated machines and non-road vehicles; and
To maintain the wheel washing facilities provided at every construction site exit where practicable are functioning properly.
Construction Noise Impact
To keep inspect the noise sources inside the site;
To keep space out noisy equipment and position the equipment as far away as possible from sensitive receivers; and
To maintain temporary noise barriers for operations of noisy equipment near the noise sensitive receivers, if necessary.
Water Impact
To maintain the cover for open stockpile of and exposed slope;
To keep reviewing and updating temporary drainage system;
To maintain the earth bunds or sand bag barriers on site to direct stormwater to silt removal facilities;
To maintain and ensure the silt removal facilities are functioning properly;
To maintain the wheel washing facilities provided at every construction site exit where practicable are functioning properly; and
To divert the muddy water at the retention pond to the wetsep for treatment before discharging out.
Waste/Chemical Management
To check for any accumulation of waste materials or rubbish on site;
To avoid any discharge or accidental spillage of chemical waste or oil directly from the site;
To maintain the drip tray well to prevent oil and chemical leakage; and
To avoid improper handling, storage and dispose of oil drums or chemical containers on site.
Ecology
To erect and maintain the protection fence around the retained trees / conservation species;
To keep the tree protection zone large enough to protect the tress; and
To remove the construction materials within the tree protection zone.
Landscape and Visual
To erect and maintain the protection fencing and tree protection zone around the preserved trees;
To remove the construction materials within the tree protection zone; and
To keep the tree protection zone large enough to protect the tress.
1