|
|
Page No. |
|
EXECUTIVE
SUMMARY |
|
|
Introduction |
5 |
|
Environmental Monitoring and Audit Progress |
5 |
|
Breaches of Action and Limit Levels |
5 |
|
Construction Noise |
5 |
|
Air Quality |
6 |
|
Ecological Monitoring |
6 |
|
Environmental Non-Compliance |
6 |
|
Environmental Complaint |
6 |
|
Notification of Summons and Successful
Prosecutions |
6 |
|
Reporting Changes |
6 |
|
Future Key Issues |
6-7 |
|
|
|
INTRODUCTION |
|
|
|
Purpose of the report |
8 |
|
Structure of the report |
8 |
|
|
|
2 |
PROJECT INFORMATION |
|
|
Background |
9 |
|
Project Organization |
9-10 |
|
Summary of Construction Works Undertaken
During Reporting Month |
10 |
|
Construction Programme |
10 |
|
Status of Environmental Licences,
Notifications and Permits |
10-11 |
|
Summary of EM&A Requirement |
11 |
|
Status of Compliance with Environmental
Permits Conditions |
11-12 |
|
|
|
3 |
NOISE MONITORING |
|
|
Monitoring Requirements |
13 |
|
Monitoring Location |
13 |
|
Monitoring Equipment |
13 |
|
Monitoring Parameters, Frequency and
Duration |
14 |
|
Monitoring Methodology and QA/QC Procedures |
14-15 |
|
Maintenance and Calibration |
15 |
|
Results and Observations |
15-16 |
|
Event and Action Plan |
16 |
|
|
|
4 |
AIR QUALITY MONITORING |
|
|
Monitoring Requirements |
17 |
|
Monitoring Location |
17 |
|
Monitoring Equipment |
17-18 |
|
Monitoring Parameters, Frequency and
Duration |
18 |
|
Monitoring Methodology and QA/QC Procedure |
18-19 |
|
Results and Observations |
19-20 |
|
Event and Action Plan |
20 |
|
|
|
5 |
LANDSCAPE AND VISUAL MONITORING |
|
|
Monitoring Requirements |
21 |
|
|
|
6 |
ECOLOGICAL MONITORING |
|
|
Monitoring of Flora Species of Conservation
Interest |
22 |
|
Post-Transplantation Monitoring and
Maintenance Programme |
22-23 |
|
Results and Observations |
23-24 |
|
Precautionary Measure for Butterfly Species
of Conservation Interest |
24 |
|
Precautionary Measures to Minimize Indirect
Disturbance on Ecology |
24 |
|
|
|
7 |
ENVIRONMENTAL SITE INSPECTION |
|
|
Site Audits |
25-26 |
|
Implementation Status of Environmental
Mitigation Measures |
26 |
|
Solid and Liquid Waste Management Status |
26 |
|
|
|
8 |
ENVIRONMENTAL NON-CONFORMANCE |
|
|
Summary of Exceedances |
27 |
|
Summary of Environmental Non-Compliance |
27 |
|
Summary of Environmental Complaint |
27 |
|
Summary of Environmental Summon and
Successful Prosecution |
27 |
|
|
|
9 |
FUTURE KEY ISSUES |
|
|
Key Issues in the Coming Three Months |
28-29 |
|
Monitoring Schedule for the Next Month |
29 |
|
|
|
10 |
CONCLUSIONS AND RECOMMENDATIONS |
|
|
Conclusions |
30 |
|
Recommendations |
30-31 |
LIST OF
TABLES
Table I Summary
Table for EM&A Activities in the Reporting Month
Table II Summary
Table for Events Recorded in the Reporting Month
Table 2.1 Key
Contacts of the Project
Table 2.2 Status
of Environmental Licences, Notifications and Permits (Contract No. SSK509)
Table 2.3 Summary
Table for Status of Compliance / Required Submission
Table 3.1 Location
for Noise Monitoring Stations
Table 3.2 Noise
Monitoring Equipment
Table 3.3 Noise
Monitoring Parameters, Duration and Frequency
Table 3.4 Summary
Table of Noise Monitoring Results during the Reporting Month
Table 3.5 Observation
at Noise Monitoring Stations
Table 4.1 Location
for Air Quality Monitoring Locations
Table 4.2 Air
Quality Monitoring Equipment
Table 4.3 Impact
Dust Monitoring Parameters, Frequency and Duration
Table 4.4 Summary
Table of 1-hour TSP Monitoring Results during the Reporting Month
Table 4.5 Observation
at Dust Monitoring Stations
Table 7.1 Observations
and Recommendations of Site Audit
LIST OF
FIGURES
Figure 1 Site
Layout Plan
Figure 2 Location
of Air Quality Monitoring Stations
Figure 3 Location
of Noise Monitoring Stations
LIST OF
APPENDICES
Appendix A Construction Programme
and Proactive Environmental Protection Proforma
Appendix B Action and Limit Levels
Appendix C Copies of
Calibration Certificates
Appendix D Environmental
Monitoring Schedules
Appendix E Air Quality Monitoring
Results and Graphical Presentation
Appendix F Noise Monitoring
Results and Graphical Presentation
Appendix G Weather Condition
Appendix H Ecological Monitoring
Records
Appendix I Event
Action Plans
Appendix J Summary of
Exceedance
Appendix K Environmental
Mitigation Implementation Schedule (EMIS)
Appendix L Waste Generation
in the Reporting Month
Appendix M Complaint Log
Appendix N Summary of Successful
Prosecution
Appendix O The potential
seriousness of the forthcoming environmental impacts and the use of machineries
Appendix P A List of
Machineries Used in Construction Site
Appendix Q Wastewater Discharge
Layout Plan
EXECUTIVE
SUMMARY
Introduction
E1. This document
represents the 12th monthly report detailing the Environmental Monitoring
and Audit (EM&A)
activities for the Kong Nga Po Police Facilities Project, which operates under
Environmental Permit No. FEP-01/510/2016. This report was prepared by Ka Shing
Management Consultancy Ltd. (Ka Shing) under “Service Contract Quotation No.
PMB202/8480/2022/A01/A Provision of Environmental Team consultancy for Design
and Construction of Kong Nga Po Police Training Facilities” (hereinafter called
the “Service Contract”). The report encapsulates the EM&A activities and
findings carried out between the 1st and 31st of March 2024.
E2. On the 23rd of December 2022, a section
of the construction site was transferred to the Architectural Services
Department (ArchSD), which assumed responsibility for the building's
construction. Furthermore, ArchSD has taken on the role of maintenance agent
for the Hong Kong Police Force (HKPF) throughout the operational phase.
E3. In the month covered by this report, the
Project of Police Facilities at Kong Nga Po, which operates under Environmental
Permit No. FEP-01/510/2016, engaged in the following contractual work: Contract
No. SSK509, which encompasses the design and construction of the Kong Nga Po
Police Training Facilities.
Environmental
Monitoring and Audit Progress
E4. A summary of the EM&A
activities in this reporting month is listed in Table I below:
Table
I
Summary Table for EM&A Activities in the Reporting Month
EM&A
Activities |
Date |
Noise
Monitoring |
07, 13,
19, 25 March 2024 |
Air
Quality Monitoring |
01, 07,
13, 19, 25, 28 March 2024 |
Environmental
Site Inspection |
5,13,
20, 28 March 2024 |
Ecological
Monitoring |
28, 30 March
2024 |
Landscape
& Visual Inspection |
05, 13, 20,
28 March 2024 |
Breaches
of Action and Limit Levels
E5. Summary of the environmental exceedances
of the reporting month is tabulated in Table
II.
Construction
Noise
E6. During
the reporting month, the planned noise monitoring for construction took place
as scheduled, with no recorded incidents of the Action/Limit Levels being
exceeded.
Air
Quality
E7. Throughout
the reporting period, all planned air quality monitoring associated with
construction was executed, and there were no recorded instances where the
Action/Limit Levels were surpassed.
Table
II Summary Table for
Events Recorded in the Reporting Month
Environmental
Monitoring |
Parameter |
No. of
Non-Project related Exceedances |
No. of
Exceedance related to the Construction Works of the Contract |
Action
Taken |
||
Action
Level |
Limit
Level |
Action
Level |
Limit
Level |
|||
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
N/A |
Air Quality |
1-hr TSP |
0 |
0 |
0 |
0 |
N/A |
Ecological
Monitoring
E8. The
ecological monitoring slated for the reporting month was conducted according to
schedule. Details of the findings from this ecological monitoring for the
respective period are available in Appendix
H.
Environmental
Non-Compliance
E9. During the reporting month, no
environmental compliance violations were documented.
Environmental
Complaint
E10. No
environmental complaints were recorded during the reporting period. In the
event of any complaints, they would be documented in the Complaint Log found in
Appendix M.
Notification
of Summons and Successful Prosecutions
E11. Throughout
the month covered in this report, there were no instances of receiving
notifications regarding summons or confirmations of successful prosecutions.
Reporting
Changes
E12. On
the 23rd of December 2022, a section of the construction site was handed over
to the Architectural Services Department (ArchSD). ArchSD has taken on the task
of overseeing the construction activities for the building. This Monthly
Environmental Monitoring and Audit (EM&A) Report offers a summary of the
site operations and the status of the environmental safeguards being
implemented under the contract with ArchSD.
Future Key
Issues
E13. The major site activities for the coming three
months include:
1. Open cut
excavation
2. Removal of soil
3. Construction of
footings
4. Construction of
pile cap
5. Construction of
substructure
6. Construction of
footbridge
7. Mock up
construction
8. U.U. Lead in and
Pipe Duct Connection
E14. The
aforementioned construction activities could potentially lead to environmental
impacts, with the primary concerns centered around construction dust, noise,
water quality, and waste management. For detailed information, please refer to Appendix A regarding the
anticipated major impacts from the construction works and corresponding
recommended mitigation measures.
1
INTRODUCTION
1.1
The Architectural Services Department (ASD)
has commissioned Ka Shing Management Consultancy Ltd. (Ka Shing) as the
Environmental Team (ET) to conduct the Environmental Monitoring and Audit
(EM&A) activities for the Kong Nga Po Police Facilities Project, as
dictated by Environmental Permit No. FEP-01/510/2016.
1.2
The main construction activities for the
Project began on the 3rd of July, 2020, and the primary location at Kong Nga Po
was handed over to the Architectural Services Department (ASD) on the 23rd of
December, 2022. The ASD has assumed control over the building construction
tasks and will serve as the maintenance representative for the Hong Kong Police
Force (HKPF) once the project is operational.
Purpose of
the report
Structure of the report
1.4 The structure of the report is as
follows:
Section 1: Introduction
Section 2: Project
Information
Section 3: Noise
Monitoring
Section 4: Air
Quality Monitoring
Section 5: Landscape
and Visual Monitoring
Section 6: Ecological
Monitoring
Section 7: Environmental
Site Inspection.
Section 8: Environmental
Non-conformance
Section 9: Future
Key Issues
Section 10: Conclusions and Recommendations
2 PROJECT
INFORMATION
Background
2.1 The
Project mainly includes construction and operation of various police facilities. The
police facilities include:
(i)
a helipad;
(ii) two firing ranges; and
(iii) other facilities, associated
infrastructure & utilities, etc.
2.2 The
Project falls under the category of a Designated Project as defined by the
Environmental Impact Assessment Ordinance (EIAO). In October 2016, an
Environmental Impact Assessment (EIA) Report (Report No.: AEIAR-201/2016) was
approved for the Project in accordance with the EIA Study Brief (No.
ESB-276/2014) and the Technical Memorandum on Environmental Impact Assessment
Process (EIAO-TM). The corresponding Environmental Permit (EP no.:
FEP-01/510/2016) was issued by the Director of Environmental Protection (DEP).
2.3 As per the approved Environmental
Monitoring and Audit (EM&A) Manual, a comprehensive air quality and noise
monitoring program is recommended during the construction phases of the Project
to assess and monitor potential dust and noise nuisances. Prior to the
commencement of the Project's construction works, baseline air quality and
noise monitoring were conducted by the previous Environmental Team (Wellab
Limited) from 14th March, 2020, to 2nd April, 2020, to establish the
pre-existing conditions at designated sensitive receivers.
2.4 Figure 1 displays the site layout plan for the Project.
Project
Organization
2.5 Various
stakeholders with varying degrees of participation are part of the Project's
organizational structure under Environmental Permit number: FEP-01/510/2016,
which includes:
Project Proponent – Architectural Services Department
(ArchSD)
Contractor– China State JV
Environmental Team (ET) – Ka Shing Management Consultancy
Ltd.
Independent Environmental Checker (IEC) – Acuity
Sustainability Consulting Limited
2.6 Table
2.1 summarizes the contact information for key personnel associated with
Quotation No. PMB202/8480/2022/A01/A and additional contacts linked with the
ArchSD Contract No. SSK509.
Table 2.1 Key Contacts of the Project
Party |
Role |
Contact
Person |
Phone
No. |
Fax No. |
Architectural
Services Department |
Project Proponent |
Mr. Vincent Kwok |
2867 3939 |
3542 5223 |
Contractor (China State JV) |
Site Agent |
Mr. Kelvin Chan |
6272 8828 |
2866 6325 |
Environmental
Officer |
Ms. Marian Kong |
6174 9735 |
||
Mr. LuLu Mar |
5998 8852 |
|||
Ka Shing Management
Consultancy Ltd. |
ETL |
Mr. W.H. Lee |
2618 2166 |
2120 7752 |
Acuity
Sustainability Consulting Limited |
IEC |
Ir. Y.H. Law |
2698 6833 |
2698 9383 |
Summary of
Construction Works Undertaken During Reporting Month
2.7 Significant site activities
conducted on-site during the reporting month comprised:
1. Open cut
excavation
2. Removal of soil
3. Construction of
footings
4. Mock-up
construction
5. Plate load test
6. Construction of
substructure
7. Construction of
footbridge
Construction
Programme
2.8 Appendix
A contains a version of the Contractors' construction schedules. The
primary site activities planned by the Contractor for the upcoming three months
have been examined. In Appendix O,
the expected environmental impacts' potential severity and the deployment of
equipment have been evaluated. This appendix additionally provides the
Contractor with recommendations and insights on alternative approaches aimed at
raising environmental consciousness, refining practices on the construction
site, and fostering environmental improvements.
2.9 Table
2.2 presents a consolidated overview of the pertinent environmental
protection permits, licenses, and/or notifications associated with this
Project.
Table 2.2 Status of Environmental Licences,
Notifications and Permits
Permit / Licence
No. |
Valid Period |
Status |
|
From |
To |
||
Further
Environmental Permit (FEP) |
|||
FEP-01/510/2016 |
N/A |
N/A |
Valid |
Construction Noise
Permit (CNP) |
|||
GW-RN1337-23 |
20-12-2023 |
19-03-2024 |
Expired |
GW-RN0302-24 |
19-03-2024 |
18-06-2024 |
Valid |
Notification
pursuant to Air Pollution Control (Construction Dust) Regulation |
|||
EPD Ref no.: 487864 |
N/A |
N/A |
N/A |
Billing Account for
Construction Waste Disposal |
|||
Account No. 7046289 |
18-01-2023 |
N/A |
Valid |
Registration of
Chemical Waste Producer |
|||
WPN5213-641-C4770-01 |
18-01-2023 |
N/A |
Valid |
Effluent Discharge
Licence under Water Pollution Control Ordinance |
|||
WT00043663-2023 |
21-04-2023 |
30-04-2028 |
Valid |
Summary of
EM&A Requirement
2.10 The
Environmental Monitoring and Audit (EM&A) program includes the monitoring
of construction noise, air quality, ecological conditions, and regular
environmental site audits. The specific requirements for the EM&A program
are outlined in the following sections:
l
Environmental requirements in contract documents;
l
Event / Action Plans;
l
Environmental mitigation measures, as
recommended in the Project EIA study final report;
l
All monitoring parameters; and
l
Action and Limit levels for all environmental
parameters.
Status of
Compliance with Environmental Permits Conditions
2.11 Table
2.3 provides a summary of the adherence to Environmental Permit (EP) No.
FEP-01/510/2016 and the necessary submissions connected to this Project as
stipulated by the EP.
Table 2.3 Summary Table for Status of Compliance /
Required Submission under FEP No. FEP-01/510/2016
FEP
Conditions |
Submission |
Submission
Date |
Approval
Status |
1.12 |
Commencement date of construction of the Project |
30/3/2023 |
* |
2.7 |
Proposal on the Reporting Mechanism and Curriculum
Vitae of the IEC |
20/3/2023 |
* |
2.10 |
The date of setting up the Community Liaison Hotline
and the contact details |
27/2/2023 |
* |
2.11 |
Management Organization of Main Construction Companies, at least an organization chart, names of responsible persons and their contact details |
10/3/2023 |
* |
2.12 |
Construction Works Schedule and Location Plans |
10/3/2023 |
* |
2.13 |
Layout plan for permeable pavings |
29/3/2023 Supplementary information submitted on 23/3/2024 |
For approval |
2.14 |
Landscape and visual mitigation plan |
26/6/2023 |
For approval |
2.16 |
Plan for perimeter walls/ boundary wall sat project
site and sidewalls of firing range |
1 month before
fence wall works |
For approval |
2.19 |
Submission of Helicopter Flight Plan |
1 month before commencement of operation of Helipad |
Notification |
3.3 |
Baseline Air Quality and Noise Monitoring Report |
30/3/2023 |
Deposit |
4.2 |
Internet address of a dedicated web site |
13/4/2023 |
* |
Remarks: *
Approval not required in FEP-01/510/2016
3 NOISE MONITORING
Monitoring
Requirements
3.1 Following the EM&A
Manual, monitoring of construction noise was performed by measuring the
A-weighted equivalent continuous sound pressure level (Leq) to track noise
generated by construction operations. Each monitoring station is scheduled for
weekly noise assessments, with one set of readings to be taken from 0700 to
1900 hours on typical weekdays. The predefined Action/Limit Levels for the
environmental monitoring activities are presented in Appendix B.
Monitoring
Location
3.2 As
per Section 3.2.3 of the EM&A Manual, impact noise monitoring took place at
fourteen specified noise monitoring stations. Following the guidelines of the
Project's Environmental Impact Assessment (EIA) report, noise monitoring
stations situated within a 300-meter radius of the Project's boundary were
taken into account. Consequently, six noise monitoring stations identified as
relevant monitoring locations are depicted in Figure 3. The specific locations
of these noise monitoring stations are detailed in Table 3.1.
Table 3.1
Location of Noise Monitoring Stations
Monitoring
Station |
Location
of Measurement |
NM9 |
Village House, Kong
Nga Po |
NM10 |
Village House, Kong
Nga Po |
NM11 |
Village House, Kong
Nga Po |
NM12 |
Village House, Kong
Nga Po |
NM13 |
Village House, Kong
Nga Po |
NM14 |
Village House, near
Man Kam To Road |
Monitoring Equipment
3.3 Impact
noise monitoring was carried out using Integrating Sound Level Meters. These
meters, classified as Type 1, are capable of providing continuous readings of
noise levels, including the equivalent continuous sound pressure level (Leq)
and percentile sound pressure level (Lx), and they conform to the
specifications of International Electrotechnical Commission Publications
651:1979 (Type 1) and 804:1985 (Type 1). The noise monitoring equipment
utilized is summarized in Table 3.2. The calibration certificates for
these devices can be found in Appendix C.
Table 3.2 Noise
Monitoring Equipment
Equipment |
Model |
Quantity |
Sound Level Meter |
RION NL-52 |
1 |
Sound Calibrator |
Castle GA607 |
1 |
Monitoring Parameters, Frequency and Duration
3.4
Table 3.3 encapsulates the variables monitored, the
frequency of monitoring, and the total time span of the noise monitoring
activities. The schedule for noise monitoring can be located in Appendix D.
Table 3.3 Noise
Monitoring Parameters, Duration and Frequency
Monitoring
Stations |
Parameter |
Duration |
Frequency |
Measurement |
NM9 |
L10(30 min.) dB(A)[2] |
0700-1900 hrs on normal weekdays |
Once per week |
Free field[1] |
NM10 |
Free field[1] |
|||
NM11 |
Façade |
|||
NM12 |
Façade |
|||
NM13 |
Free field[1] |
|||
NM14 |
Free field[1] |
Remarks:
[1]:
Correction of +3dB (A) for Free-field Measurement.
[2]:
A-weighted equivalent continuous sound pressure level (Leq). It is the constant
noise level which, under a given situation and time period, contains the same
acoustic energy as the actual time-varying noise level.
L10 is the
level exceeded for 10% of the time. For 10% of the time, the sound or noise has
a sound pressure level above L10.
L90 is the
level exceeded for 90% of the time. For 90% of the time, the noise level is
above this level.
Monitoring Methodology and QA/QC Procedures
3.5 The
procedures for noise monitoring were conducted in this manner:
- The sound level meter was mounted on a tripod,
positioned 1 meter away from the outside of the noise-sensitive facade and at a
height of 1.2 meters above ground level;
- To achieve free field measurement conditions, the meter
was placed at a distance from any reflective surfaces, and the measured noise
levels were then corrected by adding +3 dB(A);
-
The battery's condition was examined to guarantee the proper operation of the
meter;
- The settings for parameters like frequency weighting,
time weighting, and measurement duration were established as detailed
below:
-frequency
weighting: A
-time weighting: Fast
-time measurement: Leq(30 min.) dB(A)
- Noise levels were measured as six consecutive Leq,
5-minute readings during the hours when restrictions did not apply
(specifically, from 0700 to 1900 hrs on normal
weekdays).
- Calibration of the meter was performed before and after
each noise measurement session using a Calibrator set to 94.0 dB at 1000 Hz.
Should there be a discrepancy greater than 1.0 dB in calibration levels pre-
and post-measurement, the data would be deemed invalid. A repeat measurement
would then be necessary following recalibration or repair of the equipment.
- Throughout the monitoring period, parameters such as
Leq, L90, and L10 were documented. Observations regarding site conditions and
noise origins were also noted on a standard recording form.
- Noise measurements were temporarily halted during
instances of significant intrusive noise (for example, barking dogs or
helicopter sounds), where feasible. An observation record for the measurement
period was to be provided.
- Noise monitoring was suspended in conditions of fog,
rain, or when wind speeds were consistently above 5 m/s, or during gusts
surpassing 10 m/s. Wind speeds were verified using a portable anemometer
capable of measuring speed in meters per second (m/s).
Maintenance and Calibration
3.6 Every
three months, the microphone head of the sound level meter and the calibrator
was gently wiped clean using a soft fabric.
3.7 Annually
the sound level meter and calibrator underwent inspection and calibration.
3.8 Before
and after conducting each noise measurement, the precision of the sound level
meter must be verified with an acoustic calibrator that produces a set sound
pressure level at a specific frequency. Only when the pre- and post-measurement
calibration levels are within a 1.0 dB range of each other will the
measurements be considered valid.
Results and Observations
3.9 Table
3.4 provides a summary of the noise monitoring outcomes. For an in-depth
account and visual depiction of the noise monitoring, refer to Appendix F.
A summary of the meteorological data for the reporting period is compiled in Appendix G.
Table 3.4
Summary Table of Noise Monitoring Results during the Reporting Month
Monitoring
Station |
Average |
Range |
Baseline
Level |
Limit
Level |
Leq (30
min) dB(A) |
Leq (30
min) dB(A) |
dB(A) |
dB(A) |
|
NM9[1] |
57.9 |
49.9 – 62.7 |
55.9 |
75 |
NM10[1] |
58.4 |
55.0 – 62.5 |
52.8 |
|
NM11 |
49.5 |
44.1 – 62.2 |
46.4 |
|
NM12 |
48.0 |
43.8 – 51.4 |
54.7 |
|
NM13[1] |
56.2 |
47.9 – 65.7 |
61.3 |
|
NM14[1] |
44.9 |
42.8 – 49.7 |
59.6 |
Remarks: [1]: Correction of +3dB (A) for Free-field
Measurement.
3.10 Noise
monitoring related to construction activities took place according to the
planned schedule for the month reported. There were no instances where the
Action/Limit Levels were surpassed. A summary of exceedance records for the
reporting month can be found in Appendix
J.
3.11 Based
on observations made in the field, the primary sources of noise detected at the
allocated noise monitoring stations during the reporting month are as outlined
below:
Table 3.5
Observation at Noise Monitoring Stations
Monitoring
Station |
Major
Noise Source |
NM9 |
Loading &
unloading, Road traffic, Excavation works |
NM10 |
Loading &
unloading, Road traffic, Excavation works |
NM11 |
Road traffic |
NM12 |
Loading &
unloading, Road traffic |
NM13 |
Loading &
unloading, Road traffic |
NM14 |
Dog barking, Road
traffic |
Event and Action Plan
3.12 If
any non-compliance with the criteria related to the project arises, measures
will be taken following the procedures outlined in the Event Action Plan
provided in Appendix I.
4 AIR QUALITY
MONITORING
Monitoring
Requirements
4.1 As
per the EM&A Manual, 1-hour Total Suspended Particulates (TSP) monitoring
was carried out to keep track of the air quality associated with the Works
Contracts. The predetermined Action/Limit Levels for the air quality monitoring
activities are detailed in Appendix B.
4.2 Monitoring
for 1-hour Total Suspended Particulates (TSP) impacts was performed at a
minimum of three times within each six-day period at a designated air quality
monitoring station.
Monitoring
Location
4.3 In
line with Section 2.2.5 of the EM&A Manual, impact air quality monitoring
took place at two specified monitoring stations for the Project, as depicted in
Figure 2. The positions of the air quality monitoring stations are detailed in Table
4.1.
Table 4.1 Location for Air Quality
Monitoring Stations
Monitoring
Station |
Location
of Measurement |
AM1 |
Village House, Kong
Nga Po |
AM2 |
Village House, Kong
Nga Po |
Monitoring
Equipment
4.4 Due
to the denial by local villagers to set up a High-Volume Sampler (HVS) for
1-hour Total Suspended Particulates (TSP) monitoring at the chosen locations
and the inability to secure an electricity supply for the HVS, direct-reading
dust meters were utilized instead to conduct the 1-hour TSP monitoring.
Direct-reading dust meters are widely accepted instruments for measuring 1-hour
TSP levels and have been used in the same infrastructure project. The issue to
use direct-reading dust meters was presented to the Independent Environmental
Checker (IEC). The application of the direct-reading dust meter allows for
immediate and straightforward results, facilitating timely EM&A reporting
and the execution of the event and action plan. To ensure the validity and
accuracy of the readings obtained by the direct-reading method, the HVS
performed 1-hour sampling on a bi-monthly schedule.
4.5 Table 4.2 provides a summary of
the apparatus employed in the impact air quality monitoring program. Copies of
the calibration certificates for the equipment can be found in Appendix C.
Table 4.2 Air
Quality Monitoring Equipment
Equipment |
Model
and Make |
Quantity |
Dust Monitor |
SIBATA (LD-3B) |
2 |
4.6 Weather data was sourced from the
"Hong Kong Observatory - General Weather Conditions during the Monitoring
Period (March 2024)" detailed in Appendix G, which was used as a
substitute approach to acquire representative wind data.
4.7 During the monitoring days, the field staff also documented the prevailing
weather conditions, such as whether it was sunny, cloudy, or rainy.
Monitoring
Parameters, Frequency and Duration
4.8 Table 4.3
encapsulates the monitoring variables and the regularity of impact dust
assessments conducted throughout the Works Contracts operations. The schedule
for air quality observation for the month in question is presented in Appendix D.
Table 4.3 Impact Dust Monitoring
Parameters, Frequency and Duration
Parameters |
Frequency |
1-hr TSP |
Three times/ 6 days |
Monitoring Methodology and QA/QC Procedure
1-hour TSP Air Quality Monitoring
Instrumentation
4.9
The air quality monitoring utilized a direct reading dust meter, as indicated
in Table 4.2.
4.10 The
procedures for operating the dust meter adhere to the guidelines set forth in
the Manufacturer’s Instruction Manual, as described below:
- Upon
activating the Model LD-3B, the preset time that appears on the lower-left side
of the liquid crystal display reads [01 min].
- Pressing
the start/stop switch once under these conditions initiates a 1-minute
measurement.
The duration of this measurement is determined by the
preset time shown on the display.
- The liquid crystal display also features a countdown
timer on its lower-right side.
4.11 The portable
dust meter operates using a light scattering method to indicate dust levels.
Particles emit scattered light when exposed to a beam in a dark room, and the
amount of scattered light is proportional to the mass concentration of the
particles. The results provided by the portable dust meter are measured in
Counts Per Minute (CPM). To convert CPM to mass concentration (μg/m3),
it is necessary to determine the relationship between the readings of the
portable dust meter and the High Volume Sampler (HVS). The calibration
procedures for the Portable Dust Meter, as provided by a HOKLAS accredited
laboratory, are described below:
-Setup a calibrated HVS on site
and pre-conduction and pre-weight a serious of filter for calibration of
portable dust meter.
-Setup the portable dust meter
side by side with the HVS. The height of the portable dust meter should be on
the same level as the HVS air inlet.
-Mount the filter on the HVS
and start air sampling of the HVS and portable dust meter on the same time for
1 hour.
-Collect filter in the HVS and
record the reading in the portable dust meter.
-Repeat another one hour air
monitoring. During the monitoring hour, generate dust by disturb the dust tray
by a card board.
-Total 5 one hour air
monitoring will carry out, the frequency for dust generate should increase for
each hour monitoring.
-Calculate the result of the
HVS by the weight difference of the filter and the flow rate.
-Prepare a graph and work out
the relation between the HVS and the portable dust meter. (Slope and constant)
Maintenance/Calibration
4.12 The
direct dust meters required the following maintenance and calibration:
- The dust meter must be checked and calibrated against a
High Volume Sampler (HVS) to validate the precision and accuracy of the
readings obtained through the direct reading method. This calibration should be
performed bi-monthly during all phases of the air quality monitoring.
- The correlation between the dust meter and HVS in
measuring TSP was established by directly comparing the mass of dust particles
collected on a filter paper by the HVS against the dust meter's reading. For
accurate calibration, both the dust meter and the HVS should be turned on and
off at the same location and at the same time.
- The correlation coefficient was verified to confirm the
relationship between the readings from the dust meter and the HVS. This
correlation factor was ascertained by comparing the outcomes from both the HVS
and the dust meter.
- Prior to the initiation of dust monitoring, a check
must be conducted to verify that all equipment is operational and has the
necessary power supply. A zero count test was performed before and after each
monitoring session to ensure accuracy.
Results and Observations
4.13 The
outcomes of the 1-hour TSP monitoring are condensed in Table 4.4. For a
comprehensive view, detailed results and graphical representations of the
1-hour TSP monitoring data can be found in Appendix
E.
Table 4.4
Summary Table of 1-hour TSP Monitoring Results during the Reporting
Month
Monitoring
Station |
Concentration |
Action
Level, μg/m3 |
Limit
Level, μg/m3 |
|
(μg/m3) |
||||
Average |
Range |
|||
AM1 |
66 |
55 – 72 |
308 |
500 |
AM2 |
70 |
58 – 80 |
311 |
4.14 The
1-hour TSP monitoring took place according to the planned timetable for the
reporting month, and there were no instances of exceeding the established
Action/Limit Levels.
4.15 Based on field observations,
the primary sources of dust at the specified air quality monitoring stations
during the reporting month are listed in Table 4.5.
Table 4.5 Observation at Dust
Monitoring Stations
Monitoring
Station |
Major
Dust Source |
AM1 |
Equipment operation and movement / road traffic,
exposed site area, site vehicle |
AM2 |
Road traffic, exposed site area, site vehicle / equipment
operation and movement, vehicle / equipment operation and movement at
warehouse nearby |
Event and Action Plan
4.16 In the event of a
project-related violation of the criteria, measures will be taken as specified
by the Event Action Plan detailed in Appendix
I.
5 LANDSCAPE
AND VISUAL MONITORING
Monitoring Requirements
5.1
The EIA Report recommends implementing strategies to
mitigate impacts on landscape and visual resources throughout
both the construction and operational phases of the Project.
5.2 The
execution and upkeep of compensatory planting for landscaping are critical
components of this process and must be monitored to confirm their complete
fulfillment. It is essential to promptly address any potential clashes between
the proposed landscaping efforts and other Project tasks or operational needs
to ensure that the mitigation measures' objectives are not compromised.
Furthermore, the enforcement of the mitigation measures advised by the EIA will
be tracked continuously through the site audit program for the construction
phase.
5.3 The
Environmental Team (ET) carried out a fortnightly review of the execution of
measures aimed at mitigating landscape and visual impacts as part of the weekly
site audits. The findings and observations from these audit sessions are
encapsulated in Table 7.1, while the status of implementation can be
found detailed in Appendix K.
6 ECOLOGICAL
MONITORING
Monitoring of Flora Species of Conservation Interest
6.1 In
line with Section 8.3.2 of the EM&A Manual, a temporary protective barrier
must be installed around the plant species of conservation significance
identified in the detailed vegetation survey throughout the construction phase.
This barrier should be well-maintained and regularly checked to ensure its
effectiveness. Monthly checks of each plant species of conservation interest,
as pinpointed in the detailed vegetation survey, are required during the
construction phase to ensure that these species remain unaffected by the
project's construction activities.
6.2 The
monitoring aims to oversee the prompt execution of suitable environmental
management practices and the application of mitigation measures concerning the
preserved and relocated specimens of flora species of conservation interest.
The correct setup and upkeep of the temporary protective fence surrounding
these specimens were examined to assess its efficacy. The protective measures
outlined in the approved transplantation proposal's implementation schedule
were supervised.
6.3 As
per the sanctioned detailed vegetation survey report and transplantation
proposal, it was determined that 71 Brainea insignis
specimens, 41 Spiranthes sinensis specimens, and 3 Aquilaria sinensis specimens should be
relocated to the designated receiving site. Additionally, it was decided to
preserve in situ 51 Keteleeria fortunei
specimens, along with 26 small seedlings of Keteleeria fortunei and 7 small seedlings of Aquilaria sinensis, in the vicinity of
Kong Nga Po Road near the Police Dog Unit and the Force Search Unit Training
School.
Post-Transplantation Monitoring and Maintenance Programme
6.4 In
line with the accepted transplantation proposal, the Contractor is mandated to
carry out post-transplantation monitoring weekly for the first three months,
and then monthly for the remainder of the 12-month establishment phase as well
as the subsequent post-establishment phase, continuing until the construction
phase of the Project concludes. This routine monitoring is critical for
promptly identifying the growth condition of the transplanted species, any signs
of construction work within or in the vicinity of the receptor site, and any
changes in the environmental conditions of the receptor site.
6.5 For the
initial year of acclimatization, it was advised to carry out maintenance
activities to promote the robust growth of the transplanted species.
Considering the state of the transplanted organisms following the 12-month
establishment period, it was advised that maintenance activities continue
through the Post-establishment Period until the completion of the Construction
Phase. It was recommended to water the transplants daily for the first three
months following the move, as well as throughout periods of drought, to
maintain soil moisture. Additional maintenance tasks, such as mulching and
weeding, should be performed as necessary.
Results and Observations
6.6 During the
reporting month, the Contractor carried out monthly evaluations of the flora
species of conservation interest on the 30th of March 2024. The enforcement of
the protective measures detailed in the approved transplantation proposal was
reviewed, along with the maintenance of the temporary protective fencing. Appendix H contains the photographic
documentation and checklists from the monthly assessments. The health of the
transplanted and retained species was generally observed to be average to poor.
The Contractor was urged to keep a vigilant eye on the transplanted species and
to implement the protective measures as specified in the approved
transplantation proposal to safeguard these species. Furthermore, the
Contractor was given the following directives:
1)
To provide new identification tags for any Brainea insignis that were missing them;
2)
To substitute any plant labels at the receptor site that had become illegible
due to fading;
3)
To refer to the soil improvement guidelines published by the Greening,
Landscape and Tree Management Section (GLTMS) of the Development Bureau (2022)
for application in the monitoring and upkeep of the transplanted plant species;
4)
To set up shade nets;
5)
To ensure the soil remains moist by adhering to the necessary daily watering
schedule.
Transplanted Brainea
insignis and Spiranthes sinensis
6.7 From May
21st to 27th, 2020, 71 Brainea insignis specimens and 41 Spiranthes sinensis specimens were relocated to
the receptor site. The detailed account of the transplantation process was
compiled in a Transplantation Report and forwarded to ET(Wellab), IEC(Acuity),
and the Supervisor (AECOM) for their examination and documentation. Monitoring
after transplantation took place weekly for the initial three months (from June
to August 2020) and then monthly throughout the subsequent 12-month
establishment period, as well as the post-establishment phase, culminating with
the conclusion of the construction phase of the Project. The Contractor was
responsible for tracking the health of the transplanted species and carried out
maintenance measures such as watering, mulching, and weeding during the first
year to nurture the transplanted species' healthy development. Monitoring of
the transplanted Brainea insignis and Spiranthes sinensis took place on November 25th, 2023, within the reporting
period, with the findings documented in Appendix
H. Particular attention was given to the transplanted Brainea insignis specimens that were impacted by a bushfire on February
2nd, 2021, with their progress detailed in the post-transplantation monitoring
records. The health of the preserved species was noted to be generally fair.
The Contractor was advised to maintain vigilant monitoring of these species and
to enforce the stipulated protective measures to ensure their continued
preservation.
6.8 During
the monthly checks, it was observed that there were no construction operations
or storage of equipment taking place within the receptor site. The temporary
protective barrier had been correctly installed and was being well-maintained
to safeguard the transplanted species.
Precautionary Measure for Butterfly Species of
Conservation Interest
6.9
As stipulated by FEP Condition 2.17, to
reduce the impact on butterfly species of conservation concern, efforts shall
be made to improve the new grassland habitats within the Project site. This
enhancement shall be achieved by cultivating suitable plant species that serve
as the larval food source for butterflies of conservation interest, like the
Small Three-Ring, thereby supporting the well-being of these species.
6.10
The restoration of grassland zones within the
Project must be completed prior to the initiation of the Project's operational
phase. Information regarding the plant species to be used as larval food plants
for butterflies, along with the design and execution details, will be
subsequently provided under the building works contract of ArchSD.
Precautionary Measures to Minimize Indirect Disturbance
on Ecology
6.11
As outlined in Section 9.7.3 of the EIA
Report, implementing mitigation strategies for air, noise, water, waste, and
landscaping can serve as preventative actions to avert and lessen any secondary
effects of disturbance or pollution resulting from construction activities on
the surrounding ecology and habitats outside the site. The Environmental Team
(ET) conducted weekly site audits to oversee the prompt adoption of appropriate
environmental management practices and the execution of mitigation measures at the
Project site. The findings from these audits are consolidated in Section 7.3.
7 ENVIRONMENTAL
SITE INSPECTION
Site Audits
7.1 The
Environmental Team (ET) conducted site audits weekly to oversee the prompt
adoption of appropriate environmental management practices and the execution of
mitigation measures at the Contract site.
7.2 The
Environmental Team (ET), along with representatives from the Client and the
Contractor, conducted site audits on 5,13, 20, 28 March 2024 of the reported
month in 2024. Additionally, an audit was conducted on 20 March 2024, with the
Independent Environmental Checker (IEC).
7.3 In
the site inspections conducted over the reporting period, there were no
particular environmental concerns noted. It should be recognized that these
observations pertain solely to the moments of inspection. The findings and advice
from these audits are compiled in Table 7.1. The absence of identified
environmental issues during the joint site inspections does not exempt the
Contractor from their obligation to adhere strictly to all legal requirements,
the Particular Specifications, and the Environmental Monitoring and Audit
(EM&A) Manual.
Table 7.1 Observations
of Weekly site Inspection and advice
Parameters |
Date |
Observations |
Advice |
Air Quality |
-- |
No
specific environmental issues are observed |
-- |
Construction Noise Impact |
-- |
No
specific environmental issues are observed |
-- |
Water Quality |
-- |
No specific
environmental issues are observed |
-- |
Waste/ Chemical Management |
13-Mar-24 |
Disused steels are observed in bin
not for recycling. |
Segregation and storage of different
types of waste in different containers or skips or stockpiles to enhance reuse
or recycling of materials and their proper disposal |
Landscape and Visual |
-- |
No
specific environmental issues are observed |
-- |
Ecology |
-- |
No
specific environmental issues are observed |
-- |
Permit /Licences |
-- |
No
specific environmental issues are observed |
-- |
Others |
13-Mar-24 |
QPME Label
Missed |
QPME should be adopted as far as
applicable. |
Implementation Status of Environmental Mitigation
Measures
7.4
In accordance with the EIA Report and the
Project's EM&A Manual, the outlined mitigation measures are recommended to
be implemented throughout the construction phase. An overview of the
Environmental Mitigation Implementation Schedule (EMIS) is available in Appendix K.
Solid and Liquid Waste Management
Status
7.5 Pursuant
to the EM&A Manual, waste management practices were reviewed in the weekly
site audits to assess compliance with the Project's Waste Management Plan (WMP)
and pertinent legal and contractual obligations. The auditing process
encompassed the examination of waste handling, storage, transport, and disposal
methods.
7.6 The
Contractor has appointed Environmental Officers on-site to manage environmental
aspects, implement pollution control strategies, maintain proper site conduct,
and educate workers on waste management. Efforts to reduce waste production
include actively using Construction and Demolition (C&D) materials.
Excavated materials have been sorted and screened on-site to salvage any
recyclables. Non-reactive C&D materials were utilized on-site for backfill
and to construct the haul road surface. Furthermore, inert materials from
excavation activities were repurposed as fill in other local projects. Excess
inert C&D materials were sent to the Government’s public fill reception
facilities (PFRFs) for use in other projects. To oversee the disposal of inert
and non-inert C&D materials and prevent illegal dumping, a system is in
place where all materials are weighed by a weighbridge before leaving the site,
and the Trip Ticket System is rigorously enforced.
7.7 Contractor
is encouraged to reduce waste production by recycling or reusing materials. It
is imperative that all the mitigation strategies outlined in the EM&A
Manual and the waste management plans be thoroughly executed. A summary of the
progress in implementing waste management and reduction strategies is provided
in Appendix K.
7.8 This
Project produces inert Construction and Demolition (C&D) materials as well
as non-inert C&D materials. The non-inert variety consists of general
refuse and other waste materials that cannot be repurposed or recycled,
necessitating disposal at assigned landfill locations. Data detailing the
volume of waste resulting from the Project's construction activities over the
reporting period can be found in Appendix
L.
8 ENVIRONMENTAL
NON-CONFORMANCE
Summary of Exceedances
8.1 During
the reporting month, there were no instances where the air quality exceeded the
established Action and Limit Levels.
8.2 There
were no instances of construction noise surpassing the designated Action and Limit
Levels in the reporting period.
8.3 If
the monitoring data from any specific stations reveal that environmental
parameters have surpassed the Action/Limit Levels, then the procedures outlined
in the Event and Action Plans in Appendix
I should be executed. A summary of any exceedance records for the reporting
month can be found in Appendix J.
Summary of Environmental Non-Compliance
8.4 There
were no records of environmental compliance breaches during the reported month.
Summary of Environmental Complaint
8.5 In
the month under review, no complaints were registered. A log of all complaints
accumulated since the start of the Project is compiled in Appendix M.
Summary of Environmental Summon and Successful
Prosecution
8.6 Since
the beginning of the Project, there have been no instances of successful
environmental prosecution or receipt of summons. A comprehensive record of all
environmental summonses and successful prosecutions since the Project's
inception is documented in Appendix N.
9 FUTURE
KEY ISSUES
Key Issues in the Coming Three Months
9.1 Appendix A contains the provisional
construction schedules for the Project. Over the next three months, the
principal construction tasks to be carried out will include:
1. Open cut excavation
2. Removal of soil
3. Construction of footings
4. Construction of pile cap
5. Construction of substructure
6. Construction of footbridge
7. Mock up construction
8. U.U. Lead in and Pipe Duct Connection
9.2 Referring
to the site layout plan found in Appendix
A, which details the expected construction activities for the next three
months, the primary environmental concerns related to these activities are
likely to be construction dust, noise, water quality, waste management,
landscape and visual aesthetics, and ecological impacts. The anticipated
environmental effects have been factored into the mitigation strategies planned
for the upcoming months.
9.3 The
Contractor has advised mitigation measures for the next three months, which the
Environmental Team (ET), Independent Environmental Checker (IEC), and the
Client's Representative have reviewed through email correspondence during site
audits. The Proactive Environmental Protection Proforma, which outlines the key
site activities, potential environmental impacts, and advised mitigation
strategies, has been examined and verified by the IEC and is displayed in Appendix A.
9.4 During
construction and in periods of dry weather, dust can arise from work activities
and uncovered site areas. To mitigate dust emissions that could affect nearby
villages, the Contractor is advised to diligently apply air quality control
measures as outlined in the layout plan in Appendix
A, to the greatest extent possible. Moreover, the Contractor is reminded to
adhere to the Project Implementation Schedule detailed in the approved EIA
report/EM&A Manual, implementing suitable dust suppression tactics to curb
emissions from intensive construction tasks such as ground excavation and earth
moving. This includes managing all active work areas, bare site surfaces, and
unpaved roads, especially under dry conditions, by covering 80% of stockpiled
materials with impervious coverings and by moistening dusty substances with
water just before loading and transfer activities. This ensures materials
remain damp during handling in stockpile regions. Additionally, the Contractor
must adhere to the prescribed dust control methods under the Air Pollution
Control (Construction Dust) Regulation to prevent negative dust impacts from
the Project's construction activities.
9.5 Furthermore,
construction noise represents a significant environmental concern during the
Project's development. It is important to implement noise reduction strategies,
such as utilizing quiet machinery and installing noise barriers where relevant.
The Contractor has been prompted to regularly inspect and upkeep the
sound-dampening materials on noisy sections of plant and machinery, ensuring
there are no openings in the noise barriers. They should also actively
recognize any potential construction noise impacts to Noise Sensitive Receivers
(NSRs) and introduce adequate mitigation measures when required. Additionally,
residents in the nearby Kong Nga Po village should be informed in advance about
any potentially noisy activities at the work site.
9.6 The
Contractor is advised to uphold measures that protect water quality throughout
the construction process. This includes constructing barriers such as dikes or
embankments to prevent flooding around the perimeters of areas where soil is
being moved or excavated. Provision should be made for temporary channels to
direct runoff effectively into a designated watercourse via a trap designed to
capture sediment from the site. These sediment/silt traps should also be
integrated into the permanent drainage systems to improve the settling of
particulates. It is essential to utilize effective silt removal systems to
ensure that the effluent treated by the wastewater treatment plant complies
with the standards specified in the WPCO licenses. The Wastewater Discharge
Layout Plan, as shown in Appendix Q and provided by the Contractor,
outlines the specific pathways through which wastewater is to be conveyed from
its source to a treatment facility or point of discharge
Monitoring Schedule for the Next Month
9.7 Appendix D displays the provisional
schedule for environmental monitoring activities planned for the upcoming
month.
10 CONCLUSIONS
AND RECOMMENDATIONS
Conclusions
10.1 This
Monthly EM&A Report details the environmental monitoring and audit
(EM&A) activities conducted in March 2024, following the guidelines set out
in the EM&A Manual.
10.2 During the month in question, air quality
monitoring did not register any instances of surpassing the Action/Limit Levels.
10.3 No instances of construction
noise exceeding the established Action/Limit Levels were documented in the
reporting month's monitoring records.
10.4 Site
inspections focusing on environmental aspects took place on the 5, 13, 20, 28
March 2024. Additionally, monitoring of landscape and visual impacts was
performed on the 5, 13, 20 and 28 March 2024, and ecological monitoring was
conducted on the 28 March 2024 by ETL within the reporting month. The
Contractor also conducted monitoring on 30 March 2024. There were no records of
environmental non-compliance for the reporting month. It should be noted that
the absence of any particular environmental issues during the joint site
inspections does not exempt the Contractor from their obligation to adhere
fully to all legal requirements, the specifications outlined in the contract,
and the procedures in the EM&A Manual.
10.5 During
the reporting month, there were no complaints lodged, nor were there any
notices of summons or records of successful legal actions received.
10.6 The
Environmental Team (ET) will persist in overseeing the Environmental Monitoring
and Audit (EM&A) program. All environmental obligations are fulfilled, and
the necessary mitigation measures are properly executed.
Recommendations
10.7 Based
on the environmental audits conducted during the reporting month, the
subsequent advice was put forward:
Air
Quality Impact
l To enhance
the dust suppression measures including watering for the dust generation works,
exposed site area and haul road;
l To
minimize the indirect impacts on air quality resulting from the operation of
machineries on the construction site, one of the measures to be adopted is the
use of biodiesel B100; and
l To regular
check the valid NRMM labels are properly displayed on the regulated machines
and non-road vehicles
Construction
Noise
l To refer
to the ISO 12001:1996 or other comprehensive practices and subsequently develop
a thorough inspection and maintenance protocol for the plant and equipment,
maintaining a focus on Noise Control; and
l To
maintain temporary noise barriers for operations of noisy equipment near the
noise sensitive receivers, if necessary.
Water
Impact
l To
maintain the cover for open stockpile of and exposed slope;
l To keep
reviewing and updating temporary drainage system;
l To
maintain the earth bunds or sand bag barriers on site to direct stormwater to
silt removal facilities; and
l To divert
the muddy water at the retention pond to the wetsep for treatment before
discharging out.
Waste/Chemical
Management
l To check
for any accumulation of waste materials or rubbish on site; and
l To avoid
improper handling, storage and dispose of oil drums or chemical containers on
site.
Ecology
l To
maintain soil moisture, daily watering is required;
l To install
a shaded net;
l To refer
to the Guidelines on Soil Improvement issued by the Greening, Landscape and
Tree Management Section (GLTMS) of the Development Bureau (2022) for the
effective monitoring and maintenance of transplanted flora species; and
l The wild
plants that are growing in undesirable areas should be removed, as they compete
with the cultivated flora species of conservation interest.
Landscape
and Visual
l To remove
the construction materials within the tree protection zone; and
l To keep
the tree protection zone large enough to protect the tress.