Table of Contents



Page



No.


EXECUTIVE SUMMARY



Introduction

4


Summary of Construction Works undertaken during the Reporting Quarter

4


Environmental Monitoring and Audit Works

4-5


Air Quality

5


Construction Noise

5


Ecological Monitoring

5


Environmental Non-Compliance

5


Environmental Complaint

5


Notification of Summons and Successful Prosecutions

5


Future Key Issues

5-6

 

 

 

1

INTRODUCTION

 


Purpose of the report

7


Structure of the report

7

 

 

 

2

PROJECT INFORMATION

 


Background

8


Project Organization

8-9


Summary of Construction Works Undertaken During Reporting Quarter

9


Status of Environmental Licences, Notifications and Permits

9-10


Summary of EM&A Requirement

10

 

 

 

3

ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENT

 


Monitoring Parameters and Monitoring Locations

11-12


Monitoring Methodology and Calibration Details

12


Environmental Quality Performance Limits (Action and Limit Levels)

12


Landscape and visual

12


Ecology Monitoring

12-13


Site Audit Summary

13


Environmental Mitigation Measures

13


Status of Waste Management

13

 

 

 

4

MONITORING RESULTS

14


Weather Conditions

14


Air Quality

14


Construction Noise

14-15


Ecological Monitoring

15

 

 

 

 

 

 

5

ENVIRONMENTAL SITE INSPECTION

 


Site Audits

16


Implementation Status of Environmental Mitigation Measures

16


Solid and Liquid Waste Management Status

16

 

 

 

6

NON-COMPLIANCE (EXCEEDANCES) OF THE ENVIRONMENTAL

 


QUALITY PERFORMANCE LIMITS (ACTION AND LIMIT LEVELS)

 


Summary of Exceedances

17


Summary of Environmental Non-Compliance

17


Summary of Environmental Complaint

17


Summary of Environmental Summon and Successful Prosecution

17

 

 

 

7

FUTURE KEY ISSUES

 


Key Issues in the Coming Three Months

18-19

 

 

 

8

CONCLUSIONS AND RECOMMENDATIONS

 


Conclusions

20


Recommendations

20-22

 

 

 

LIST OF TABLES

Table I

Summary Table for Events Recorded in the Reporting Quarter

Table 2.1

Key Contacts of the Project

Table 2.2

Status of Environmental Licences, Notifications and Permits

Table 3.1

Location for Air Quality Monitoring Stations

Table 3.2

Impact Air Quality Monitoring Monitoring Parameters, Frequency and Duration

Table 3.3

Location of Noise Monitoring Stations

Table 3.4

Noise Monitoring Parameters, Duration and Frequency

Table 4.1

Summary of 1-hour TSP Monitoring Result in Reporting Quarter

Table 4.2

Summary of Noise Monitoring Result in Reporting Quarter



LIST OF FIGURES

Figure 1

Site Layout Plan

Figure 2

Location of Air Quality Monitoring Station

Figure 3

Location of Noise Monitoring Station



LIST OF APPENDICES

Appendix A

Action and Limit Levels

Appendix B

1-hour TSP Monitoring Graphical Presentation

Appendix C

Noise Monitoring Graphical Presentation

Appendix D

Event Action Plans

Appendix E

Summary of Exceedance

Appendix F

Environmental Mitigation Implementation Schedule (EMIS)

Appendix G

Site Audit Summary

Appendix H

Waste Generation in the Reporting Period

Appendix I

Complaint Log

Appendix J

Summary of Successful Prosecution

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

EXECUTIVE SUMMARY

 

Introduction

1.                     This is the 3rd Quarterly Environmental Monitoring and Audit (EM&A) Report for the Project of Police Facilities in Kong Nga Po under Environmental Permit No. FEP-01/510/2016. This report was prepared by Ka Shing Management Consultancy Ltd. (Ka Shing) under “Service Contract Quotation No. PMB202/8480/2022/A01/A Provision of Environmental Team consultancy for Design and Construction of Kong Nga Po Police Training Facilities” (hereinafter called the “Service Contract”). This report documents the findings of Environmental Monitoring and Audit (EM&A) work conducted from October to December 2023.

 

2.                     During the reporting quarterly, the following Works Contracts were undertaken for the Project of Police Facilities in Kong Nga Po under Environmental Permit No. FEP-01/510/2016:

l    Contract No. SSK509 - Design and Construction of Kong Nga Po Police Training Facilities

 

Summary of Construction Works undertaken during the Reporting Quarter

3.                     The major site activities undertaken in the reporting quarter included:

l    Open cut excavation

l    Plate load test

l    Laying blinding layer

l    Removal of soil

l    Ground Investigation

l    Pre-bored socketed-H Piling

l    Construction of footings

l    Mock-up construction

 

 

Environmental Monitoring and Audit Works

4.                     Environmental monitoring for the Project was performed in accordance with the EM&A Manual and the monitoring results were checked and reviewed. Site Inspections/Audits were conducted once per week. The implementation of the environmental mitigation measures, Event Action Plans and environmental complaint handling procedures were also checked.

 

5.                     Summary of the environmental exceedances of the reporting quarter for the Project is tabulated in Table I.

 

 

 

 

Table I          Summary Table for Events Recorded in the Reporting Quarter

Environmental Monitoring

Parameter

No. of Non-Project related Exceedances

No. of Exceedance related to the Construction Works of the Contract

Action Taken

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

N/A

Noise

Leq(30min)

0

0

0

0

N/A

 

Air Quality

6.     All construction air quality monitoring was conducted as scheduled in the reporting quarter. No Action/Limit Level exceedance was recorded in the reporting quarter.

 

Construction Noise

7.     All Construction noise monitoring was conducted as scheduled in the reporting quarter. No Action/Limit Level exceedance was recorded in the reporting quarter.

 

Ecological Monitoring

8.     All ecological monitoring was conducted as scheduled in the reporting quarter. The ecological monitoring photo records and results were shown in the relevant Monthly EM&A Reports.

 

Environmental Non-Compliance

9.     No environmental non-compliance was recorded in the reporting quarter.

 

Environmental Complaint

10.   One environmental complaint was received in the reporting quarter. The Complaint Log is presented in Appendix I.

 

Notification of Summons and Successful Prosecutions

11.   No notification of summons or successful environmental prosecutions was received in the reporting quarter.

 

Future Key Issues

12.   The major site activities for the coming three months include:

l    Open cut excavation

l    Removal of soil

l    Construction of footings

l    Construction of pile cap

l    Mock up construction

l    U.U. Lead in and Pipe Duct Connection

 

13.   Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, noise, water quality and waste management. The anticipated major impacts from the construction works and corresponding recommended mitigation measures are detailed in Appendix G of Site Audit Summary.

 


 

1      INTRODUCTION

 

1.1       Ka Shing Management Consultancy Ltd. (Ka Shing) was commissioned by the Architectural Services Department (ASD) as the Environmental Team to undertake the Environmental Monitoring and Audit (EM&A) works for the Project of Police Facilities in Kong Nga Po under Environmental Permit No. FEP-01/510/2016 to ensure that the environmental performance of the Works Contracts comply with the requirements specified in the Environmental Permits (EPs), Environmental Impact Assessment (EIA) Report and Environmental Monitoring & Audit (EM&A) Manual of the Police Facilities in Kong Nga Po Project and other relevant statutory requirements.

 

Purpose of the report

1.2       This is the 3rd Quarterly EM&A Report which summarises the impact monitoring results and audit findings for the EM&A programme during the reporting period from October to December 2023.

 

Structure of the report

1.3       The structure of the report is as follows:

Section 1: Introduction - purpose and structure of the report.

Section 2: Project Information – summarises background and scope of the Project,

site description, project organisation and contact details, construction programme, the construction works undertaken and the status of Environmental Permits/Licences during the reporting period.

Section 3: Environmental Monitoring and Audit Requirement – summarises monitoring location and parameters, monitoring programmes, monitoring frequencies, Action and Limit Levels, Event / Action Plans, and Site Audit inspection.

Section 4: Monitoring Result – summarises the monitoring results in the reporting quarter.

Section 5: Environmental Site Inspection – summarises the audit findings of the weekly site inspections undertaken within the reporting period.

Section 6: Non-Compliance of the Environmental Quality Performance Limits (Action and Limit) – summarises any monitoring exceedance, environmental complaints, environmental summons and successful prosecutions within the reporting period.

Section 7: Future Key Issues – summarises the impact forecast and monitoring schedule for the next three months.

Section 8: Conclusions and Recommendations

 

 

 

 

 

 

2             PROJECT INFORMATION

 

Background

2.1   The Project mainly includes construction and operation of various police facilities. The police facilities include:

(i)    a helipad;

(ii)   two firing ranges; and

(iii)  other facilities, associated infrastructure & utilities, etc.

 

2.2  The Project is a Designated Project under the Environmental Impact Assessment Ordinance (EIAO). An Environmental Impact Assessment (EIA) Report (Report No.: AEIAR-201/2016) for the Project was approved under EIAO in October 2016 in accordance with the EIA Study Brief (No. ESB-276/2014) and the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM). The corresponding Environmental Permit was issued (EP no.: FEP-01/510/2016) by the Director of Environmental Protection (DEP).

 

2.3   According to an approved Environmental Monitoring and Audit (EM&A) Manual, an air quality and noise monitoring programme is recommended during the construction phases of the Project to monitor the expected dust and noise nuisances. Baseline air quality and noise monitoring were conducted by previous ET (Wellab Limited) from 14th March 2020 to 2nd April 2020 to establish the background conditions of the designated sensitive receivers prior to the commencement of the Project’s construction works.

 

2.4   The site layout plan for the Project is shown in Figure 1.

 

Project Organization

2.5   Different parties with different levels of involvement in the Project organization under EP no.: FEP-01/510/2016 include:

Project Proponent – Architectural Services Department (ArchSD)

Contractor– China State JV

Environmental Team (ET) – Ka Shing Management Consultancy Ltd.

Independent Environmental Checker (IEC) – Acuity Sustainability Consulting Limited

 

2.6   The key personnel contact names and numbers under Quotation No. PMB202/8480/2022/A01/A and the other contact names and numbers under ArchSD Contract No. SSK509 are summarised in Table 2.1.

 

 

 

 

 

Table 2.1  Key Contacts of the Project

Party

Role

Contact Person

Phone No.

Fax No.

Architectural Services Department

Project Proponent

Mr. Vincent Kwok

2867 3939

3542 5223

Contractor

(China State JV)

Site Agent

Mr. Kelvin Chan

6272 8828

2866 6325

Senior Environmental Officer

Ms. Marian Kong

6174 9735

2866 6325

Ka Shing Management Consultancy Ltd.

ETL

Mr. W.H. Lee

2618 2166

2120 7752

Acuity Sustainability

Consulting Limited

IEC

Ir. Y.H. Law

2698 6833

2698 9383

 

Summary of Construction Works Undertaken During Reporting Quarter

2.7   The major site activities undertaken in the reporting quarterly included:

l    Open cut excavation

l    Plate load test

l    Laying blinding layer

l    Removal of soil

l    Ground Investigation

l    Pre-bored socketed-H Piling

l    Construction of footings

l    Mock-up construction

 

Status of Environmental Licences, Notifications and Permits

2.8   A summary of the relevant permits, licences, and/or notifications on environmental protection for this Project is presented in Table 2.2

 

Table 2.2  Status of Environmental Licences, Notifications and Permits

Permit / Licence No.

Valid Period

Status

From

To

Further Environmental Permit (FEP)

FEP-01/510/2016

N/A

N/A

Valid

Construction Noise Permit (CNP)

GW-RN0992-23

23-09-2023

19-12-2023

Valid

GW-RN1337-23

20-12-2023 

19-03-2024 

Valid

Notification pursuant to Air Pollution Control (Construction Dust) Regulation

 EPD Ref no.: 487864

N/A

N/A

N/A

Billing Account for Construction Waste Disposal

Account No. 7046289

18-01-2023

N/A

Valid

Registration of Chemical Waste Producer

WPN5213-641-C4770-01

18-01-2023

N/A

Valid

Effluent Discharge Licence under Water Pollution Control Ordinance

WT00043663-2023

21-04-2023

30-04-2028

Valid

 

Summary of EM&A Requirement

2.9   The EM&A programme requires construction noise monitoring, air quality monitoring, ecological monitoring and environmental site audits. The EM&A requirements are described in the following sections, including:

l     All monitoring parameters;

l     Action and Limit levels for all environmental parameters;

l     Event / Action Plans;

l     Environmental mitigation measures, as recommended in the Project EIA study final report; and

l     Environmental requirements in contract documents.

 

 

 


 

3             ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENT

 

Monitoring Parameters and Monitoring Locations

 

Air Quality Monitoring

 

3.1   In accordance with the EM&A Manual, impact 1-hour TSP monitoring was conducted to monitor the air quality for the Works Contracts. The locations of the monitoring stations are shown in Figure 2. Table 3.1 describes the location of the air quality monitoring stations.

 

Table 3.1     Location for Air Quality Monitoring Stations

Monitoring Station

Location of Measurement

AM1

Village House, Kong Nga Po

AM2

Village House, Kong Nga Po

 

3.2     Table 3.2 summarises the monitoring parameters and frequencies of impact air quality monitoring during the Works Contracts activities.

 

Table 3.2    Impact Air Quality Monitoring Parameters, Frequency and Duration

Parameters

Frequency

1-hr TSP

Three times/ 6 days

 

Noise Monitoring

 

3.3       In accordance with the EM&A Manual, construction noise monitoring were conducted to monitor the construction noise arising from the construction activities. The locations of the monitoring stations are shown in Figure 3. Table 3.3 describes the location of the noise monitoring stations.

 

Table 3.3         Location of Noise Monitoring Stations

Monitoring Station

Location of Measurement

NM9

Village House, Kong Nga Po

NM10

Village House, Kong Nga Po

NM11

Village House, Kong Nga Po

NM12

Village House, Kong Nga Po

NM13

Village House, Kong Nga Po

NM14

Village House, near Man Kam To Road

 

 

 

 

 

 

3.4       Table 3.4 summarises the monitoring parameters and frequencies of construction noise monitoring during the Works Contracts activities.

 

Table 3.4   Noise Monitoring Parameters, Duration and Frequency

Monitoring Stations

Parameter

Duration

Frequency

Measurement

NM9

L10(30 min.) dB(A)[2]

L90(30 min.) dB(A)[2]

Leq(30 min.) dB(A)[2]

(as six consecutive Leq, 5min readings)

0700-1900 hrs on normal weekdays

Once per

week

Free field[1]

NM10

Free field[1]

NM11

Façade

NM12

Façade

NM13

Free field[1]

NM14

Free field[1]

Remarks:

[1]: Correction of +3dB (A) for Free-field Measurement.

[2]: A-weighted equivalent continuous sound pressure level (Leq). It is the constant noise level which, under a given situation and time period, contains the same acoustic energy as the actual time-varying noise level.

L10 is the level exceeded for 10% of the time. For 10% of the time, the sound or noise has a sound pressure level above L10.

L90 is the level exceeded for 90% of the time. For 90% of the time, the noise level is above this level.

 

Monitoring Methodology and Calibration Details

3.5   Monitoring works/equipment were conducted/calibrated regularly in accordance with the Project Specific EM&A Manual. Copies of calibration certificates were attached in the relevant Monthly EM&A Reports.

 

Environmental Quality Performance Limits (Action and Limit Levels)

3.6   The environmental quality performance limit i.e. Action and Limit Levels were derived from the baseline monitoring results. Should the measured environmental quality parameters exceed the Action/Limit Levels, the respective action plans would be implemented. The Action/Limit Levels for each environmental parameter are given in Appendix A.

 

Landscape and visual

3.7   Bi-weekly inspection of the implementation of landscape and visual mitigation measures was conducted during weekly site audit. Most of the necessary mitigation measures have been implemented and recommended follow-up actions have been discharged by the Contractor. Details of the audit findings and implementation status are summarized in Appendix F and Appendix G.

 

Ecology Monitoring

3.8   Ecology monitoring was carried out on a monthly basis to monitor the timely implementation of proper environmental management practices and mitigation measures for the retained and transplanted individuals of flora species of conservation interest. Proper erection and maintenance of the temporary protective fence enclosing the individuals was inspected for the effectiveness. The ecological monitoring photo records and result could refer to the relevant Monthly EM&A Reports.

 

Site Audit Summary

3.9   Site audit were carried out on a weekly basis to monitor and audit the timely implementation of proper environmental management practices and mitigation measure of this Project. The observations and recommendations made during the reporting period are summarized in Appendix G.

 

Environmental Mitigation Measures

3.10 Relevant mitigation measures as recommended in the project EIA report have been stipulated in the Project EM&A Manual for the Contractor to implement. A summary of the Environmental Mitigation Implementation Schedule (EMIS) is given in Appendix F.

 

Status of Waste Management

3.11 The amount of wastes generated by the major site activities of this Project during the reporting quarter is shown in Appendix H.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4             MONITORING RESULTS

 

Weather Conditions

4.1  The detail of weather conditions for each individual monitoring session could be referred to monthly EM&A reports.

 

Air Quality

1-hr TSP Monitoring

 

4.2  All construction air quality monitoring was conducted as scheduled during the   reporting quarter.

 

4.3  No Action/Limit Level exceedance was recorded in this reporting quarter. A summary of exceedance is attached in Appendix E.

 

4.4  Table 4.1 summarizes the air quality monitoring results which were extracted from the monthly reports for this Project. The graphical presentation of the air quality monitoring results is shown in Appendix B.

 

Table 4.1        Summary of 1-hour TSP Monitoring Result in Reporting Quarter

Reporting Months

Air Quality Monitoring Station

Average

Range

Action Level

Limit Level

μg/m3

μg/m3

μg/m3

μg/m3

Oct-23

AM1

59

45 – 71

308

500

AM2

73

61 – 82

311

Nov-23

AM1

71

60 – 91

308

AM2

74

64 – 80

311

Dec-23

AM1

54

35 – 69

308

AM2

79

59 – 95

311

 

Construction Noise

4.5   All construction noise monitoring was conducted as scheduled in the reporting quarter.

 

4.6   No Action Level exceedance was recorded in this reporting month. No Limit Level exceedance was recorded. A summary of exceedance is attached in Appendix E.

 

4.7  Table 4.2 summarizes the noise monitoring results which were extracted from the monthly reports for this Project. The graphical presentations of the construction noise monitoring results are shown in Appendix C.

 

 

Table 4.2 Summary of Noise Monitoring Result in Reporting Quarter Remarks:

Reporting Months

Noise Quality Monitoring Station

Average

Range

Baseline Level dB(A)

Limit Level, dB(A)

Leq (30 min), dB(A)

Leq (30 min), dB(A)

Oct-23

NM9

57.9

54.5 – 61.9

55.9

75

NM10

52.5

50.2 – 57.1

52.8

NM11

46.7

42.8 – 49.0

46.4

NM12

49.2

46.9 – 50.9

54.7

NM13

56.0

53.8 – 58.9

61.3

NM14

46.7

43.7 – 49.4

59.6

Nov-23

NM9

56.6

46.1 – 60.7

55.9

NM10

56.6

51.5 – 62.1

52.8

NM11

48.5

46.4 – 51.2

46.4

NM12

49.4

41.8 – 61.9

54.7

NM13

55.9

53.3 – 57.9

61.3

NM14

46.3

45.3 – 48.0

59.6

Dec-23

NM9

57.2

55.4 – 58.3

55.9

NM10

51.3

50.0 – 52.7

52.8

NM11

45.8

42.8 – 47.6

46.4

NM12

46.1

42.2 – 50.1

54.7

NM13

53.1

52.6 – 53.7

61.3

NM14

43.4

42.4 – 44.0

59.6

 

            Ecological Monitoring

4.8       Monthly monitoring of flora species of conservation interest were conducted by ET as scheduled in the reporting quarter. No construction activity and equipment storage were observed within the receptor site. Temporary protective fences were found properly erected and maintained for the transplanted species.

 

4.9       According to approved transplantation proposal, the post-transplantation monitoring for transplanted Brainea insignis and Spiranthes sinensis was conducted by Contractor post-transplantation monitoring on transplanted Brainea insignis and Spiranthes sinensis was conducted once per month by the Contractor under Contract No. SSK509 from October to December 2023 during the reporting period.

 

4.10     The contractor provided maintenance works including watering, use of mulch and weeding to allow healthy growth of the transplanted species. The post-transplantation monitoring records were submitted to ET and IEC for review and were included in the relevant monthly EM&A Reports for record keeping.

 

 

 

 

5         ENVIRONMENTAL SITE INSPECTION

 

Site Audits

5.1       Site audits were carried out by ET on weekly basis in the reporting quarter to monitor the timely implementation of proper environmental management practices and mitigation measures on the project site. No non-conformance was identified and the observation and recommendations made in each individual site audit session in the reporting period are summarized in Appendix G.

 

Implementation Status of Environmental Mitigation Measures

5.2       According to the EIA Report, Environmental Permit and the EM&A Manual of the Project, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase. An updated summary of the Environmental Mitigation Implementation Schedule (EMIS) is provided in Appendix F.

 

Solid and Liquid Waste Management Status

5.3       In accordance with the EM&A Manual, waste management was audited during weekly site audit to determine if wastes are being managed in accordance with the Waste Management Plan (WMP) prepared for the Project and the relevant legislative and contractual requirements. Waste management practice including waste handling, storage, transportation and disposal were audited.

 

5.4       The Contractor is advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in the EM&A Manual and waste management plans shall be fully implemented. The status of implementation of waste management and reduction measures are summarised in Appendix F.

 

5.5      Waste generated from this Project includes inert C&D materials and non-inert C&D materials. Non-inert C&D materials are made up of general refuse and waste that cannot be reused or recycled and has to be disposed of at the designated landfill sites. The amount of wastes generated by the construction works of the Project during the reporting quarter is shown in Appendix H.

 

 

 

 

 

 

 

 

 

6      NON-COMPLIANCE (EXCEEDANCES) OF THE ENVIRONMENTAL QUALITY PERFORMANCE LIMITS (ACTION AND LIMIT LEVELS)

 

Summary of Exceedances

6.1       Environmental monitoring works were performed in the reporting quarter and all monitoring results were checked and reviewed. A summary of exceedance is attached in Appendix E.

 

6.2       No exceedance of Action/Limit Levels of air quality and construction noise was recorded in the reporting quarter.

 

6.3       No Action Level exceedance for noise monitoring was recorded. No exceedance of Limit Level of construction noise was recorded in the reporting quarter.

 

Summary of Environmental Non-Compliance

6.4       No environmental non-compliance was recorded in the reporting quarter. The observations and recommendations made in each individual site audit session were presented in Appendix G.

 

Summary of Environmental Complaint

6.5      One complaint related to water quality was received in the reporting month. No complaints related to air quality. The Cumulative Complaint Log since the commencement of the Project is attached in Appendix I.

 

Summary of Environmental Summon and Successful Prosecution

6.6       There was no successful environmental prosecution or notification of summons received in the reporting quarter. The Cumulative Log for environmental summon and successful prosecution since the commencement of the Project is presented in Appendix J.

 

 

 

 

 

 

 

 

 

 

 

 


 

7          FUTURE KEY ISSUES

 

Key Issues in the Coming Three Months

7.1       The major construction activities undertaken in the coming three months will include:

l    Open cut excavation

l    Removal of soil

l    Construction of footings

l    Construction of pile cap

l    Mock up construction

l    U.U. Lead in and Pipe Duct Connection

 

7.2       Potential environmental impacts arising from the above construction activities are mainly associated with construction dust, noise, water quality, waste management and ecology. The proactive Environmental Protection Proforma summarizing the major site activities, potential environmental impacts and recommended mitigation measures for the coming months could refer to relevant Monthly EM&A Report.

 

7.3       Dust can be generated during construction works and exposed site area in the summer months and windy weather in the upcoming dry season. To prevent high dust concentrations during the summer months, the Contractor should pay attention on the air quality mitigation measures as far as practicable to minimise the dust impact to the villages which are located adjacent to the Project works. The Contractor was also reminded to follow the Project Implementation Schedule in approved EIA report / EM&A Manual to implement appropriate dust control to reduce dust emissions from heavy construction activities (including ground excavation, earth moving, etc.) at all active works area exposed site surfaces and unpaved roads, particularly during dry weather and covering 80% of stockpiling area by impervious sheets and spraying all dusty material with water immediately prior to any loading transfer operations to keep the dusty materials wet during material handling at the stockpile areas as well as the relevant dust control practices as stipulated in the Air Pollution Control (Construction Dust) Regulation so that no adverse dust impact arising from the Project works site.

 

7.4       In addition, construction noise is also one of the key environmental issues during construction of the Project. Noise mitigation measures such as using quiet plants and noise barriers should be in place, where applicable. In addition, the Contractor was reminded to frequently check and maintain the acoustic materials wrapped on noisy part of PME and ensure no gaps between noise barriers; proactively identify any potential construction noise impact to NSRs and provide sufficient mitigation measures if necessary; and provide notification to nearby villagers in Kong Nga Po for potential noisy works at works area.

 

7.5       All other mitigation measures recommended in the Project Implementation Schedule in approved EIA report / EM&A Manual should be properly implemented and maintained as far as practicable.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

8          CONCLUSIONS AND RECOMMENDATIONS

 

Conclusions

8.1       This Quarterly EM&A Report presents the EM&A work undertaken from October to December 2023 in accordance with EM&A Manual.

 

8.2       Environmental monitoring and audit works were performed in the reporting quarter and all monitoring results were checked and reviewed.

 

            Air Quality Monitoring

8.3       Air Quality monitoring was conducted as scheduled in the reporting quarter. No Action/Limit Level exceedance was recorded.

 

            Construction Noise Monitoring

8.4       Construction Noise monitoring was conducted as scheduled in the reporting quarter. No Limit Level exceedance was recorded. No exceedance of Limit Level of construction noise was recorded in the reporting quarter

 

            Environmental Site inspections

8.5       Environmental site inspections were conducted as weekly basis in the reporting quarter. No environmental non-compliance was recorded.

 

            Environmental Complaint and Successful Prosecution

8.6      One complaint related to water quality was received in the reporting month. No complaints related to air quality.  No notification of summons or successful prosecutions was received in the reporting quarter.

 

Recommendations

8.7       The mitigation measures recommended in the EIA report and EM&A Manual are considered effective and efficient in minimizing environmental impacts due to construction of the project during the reporting quarter. The EM&A programme implemented by the ET has effectively monitored the environmental impacts arising from the construction activities and ensure the proper implementation of mitigation measures.

 

8.8       The effectiveness and efficiency of the EM&A programme will be continuously reviewed. The EM&A programme will be improved if deficiencies of the existing EM&A programme are identified.

 

8.9       According to the environmental audits performed in the reporting quarter, the following recommendations were provided to remediate any potential impacts due to the Project:

 

        Air Quality Impact

l  To maintain the cover for stockpile of dusty materials and exposed slope for dust suppression;

l  To enhance the dust suppression measures including watering for the dust generation works, exposed site area and haul road;

l  To regular check the valid NRMM labels are properly displayed on the regulated machines and non-road vehicles; and

l  To maintain the wheel washing facilities provided at every construction site exit where practicable are functioning properly.

 

        Construction Noise Impact

l  To keep inspect the noise sources inside the site;

l  To keep space out noisy equipment and position the equipment as far away as possible from sensitive receivers; and

l  To maintain temporary noise barriers for operations of noisy equipment near the noise sensitive receivers, if necessary.

 

        Water Impact

l  To maintain the cover for open stockpile of and exposed slope;

l  To keep reviewing and updating temporary drainage system;

l  To maintain the earth bunds or sand bag barriers on site to direct stormwater to silt removal facilities;

l  To maintain and ensure the silt removal facilities are functioning properly;

l  To maintain the wheel washing facilities provided at every construction site exit where practicable are functioning properly; and

l  To divert the muddy water at the retention pond to the wetsep for treatment before discharging out.

 

        Waste/Chemical Management

l  To check for any accumulation of waste materials or rubbish on site;

l  To avoid any discharge or accidental spillage of chemical waste or oil directly from the site;

l  To maintain the drip tray well to prevent oil and chemical leakage; and

l  To avoid improper handling, storage and dispose of oil drums or chemical containers on site.

           

        Ecology

l To erect and maintain the protection fence around the retained trees / conservation species;

l To keep the tree protection zone large enough to protect the tress; and

l To remove the construction materials within the tree protection zone.

           

Landscape and Visual

l To erect and maintain the protection fencing and tree protection zone around the preserved trees;

l To remove the construction materials within the tree protection zone; and

l To keep the tree protection zone large enough to protect the tress.